Does anyone know what information needs to be prepared for fire inspection and acceptance when the hotel project is completed?

1. Procedures for fire control application and acceptance

Drawing by qualified design unit-submitted to the fire department for examination and approval (3-15 days)-issued audit opinions-revised drawings according to audit opinions-re-submitted for examination-issued construction opinions-submitted original construction drawings and copies of audit opinions to the property management company for filing-construction-debugging-testing by professional units.

2. Information to be provided when the fire department submits for approval:

Decoration plan and construction drawing; Lighting, electricity plan and construction drawing; List of decoration materials and certificate of fire prevention materials; Decoration unit qualification certificate