General hotel project payment method?

At present, the project price settlement methods mainly include the following:

(1) monthly statement. Monthly periodic settlement refers to the method that the construction enterprise submits the monthly report of the completed project together with the project price settlement list, and then submits it to the Construction Bank for project price settlement after being signed by the construction unit.

(2) Settlement by sections. Settlement by stages refers to a single (or unit) project, which is divided into different construction stages according to the image progress of Zheng Shi, and the project price is settled by stages.

The general method of installment settlement is to divide the construction process into several construction progress stages according to the nature and characteristics of the project, and calculate the amount of advance payment in each stage based on the approved construction drawing budget. In the initial stage of construction, the advance payment of the first stage will be processed. After the completion of this stage, calculate the project price, submit it to the Construction Bank for review and settlement, and handle the advance payment in the next stage.

(3) One-time settlement after completion. One-time settlement after completion means that if the construction period of all construction and installation projects of a construction project or a single project is less than one year, or the contract amount of the project is less than1000000 yuan, the project price can be paid in advance on a monthly basis or in stages, and the project price can be settled at one time after completion.