How to handle the real estate license of hotel projects under construction
1. Acceptance by Planning Bureau:
Purpose: Change the copy of planning permit into the original
Preparation materials:
1. Deputy certificate of planning permit for construction project
2. Land certificate
3. Application for planning acceptance (opinion of town government)
4. Topographic map survey;
5. Property survey results
6. General plan;
7. Single plan (elevation, section and side view)
Article 4: First, carry out topographic mapping of real estate (contact planning and design institute), and send the mapping results to the Planning Bureau for warehousing in exchange for warehousing notice
Article 5: contact the Housing Authority for on-site measurement
2. Acceptance of quality supervision station:
Purpose: to obtain the unit project completion certificate (quality supervision)
materials sent to archives:
1. project application (project report)
2. project feasibility study report and reply
3. land application and reply
4. red line map of land location
5. state-owned land use certificate (copy)
6. construction land planning permit (original)
. Red line map of engineering planning (plane layout, which must be stamped with the business seal of the Planning Bureau)
9. Bidding documents (or direct contracting documents), bid-winning (undertaking) notice
1. Geological survey report
11. Construction drawing review and audit documents of environmental protection, fire protection, earthquake resistance and civil air defense management departments
12. Survey design, preliminary design or expanded design. Entrusting documents such as drilling
15, quality supervision declaration form (including quality supervision notice)
16, construction permit
17, construction contract (and subcontract)
18, project budget
19, image data (including basic and concealed works)
After receiving the receipt from the archives, Send it to the quality supervision station together with the following information
1. Foundation acceptance report (provided by the construction unit)
2. Subject acceptance report (steel structure acceptance report, Provided by the construction unit)
3. Receipt from the archives
4. Inspection report (provided by the construction unit)
5. Evaluation report (provided by the supervision unit)
6. Completion acceptance report (provided by the construction unit)
3. Fire fighting acceptance
Purpose: materials required for handling the real estate license
:
Project completion acceptance report (show the original and receive a copy) Note: You can only get it after the quality supervision station has accepted it. That is, project completion acceptance certificate
4, fire protection product certificate, acceptance report and form (original)
5, legal identity and qualification grade certificate of construction unit, project supervisor and testing unit
6, complete set of as-built drawings (blueprint with stamp and completion seal)
7, pressure test report
4, environmental protection trial production application (3 months). Sewage pipe map
5. What procedures and materials are needed to handle the real estate license:
1. Original planning permit (copy, archive seal)
2. Copy of construction permit
3. Approval from the National Development and Reform Commission (copy stamped with archive seal)
4. General plan (seal of planning bureau)
5. Articles of association
. Copy)
9. Land certificate (show original and copy)
1. Project completion record form (construction bureau window)
11. Fire protection and environmental protection acceptance.
VI. About the record form of project completion:
With the certificate of project completion acceptance stamped by the archives, go to the quality supervision station to receive the quality supervision report and other materials, and go to the window of the Construction Bureau for record, which requires two originals (record form, with the seal of each unit) and the fire protection and environmental protection acceptance permit, that is, the notice of acceptance of the fire protection record of the construction project and the registration card of the environmental protection assistant for the completion of the construction project.
- Previous article:What should I do if the hotel is locked against theft?
- Next article:Does Shijiazhuang Laiyuan Huazhong Holiday Hotel pay wages?
- Related articles
- /kloc-I want to travel to Tibet in early February and ask my relatives for advice.
- Sudirman Cup Back to Hotel
- Zhuhai free travel design route
- Want to know: bus route information from Yichun Railway Station in Yichun City to No.399 Zhongshan West Road in Yichun Vocational Technical College.
- What are the scenic spots in Weizhou Island? What's delicious in Weizhou Island?
- Bus from Pingshan Bus Station to Guichong Holiday Hotel
- Di Chin Baota Fenghua Building Decoration
- Take your girlfriend to the hotel. Do we both have to bring ID cards?
- What booking services does the travel agency need to complete before the tour group arrives?
- Why don't KFC and McDonald's issue consumption invoices?