Traditional Culture Encyclopedia - Hotel accommodation - Detailed implementation rules for special supervision of high-temperature prevention construction and flood prevention and typhoon prevention?

Detailed implementation rules for special supervision of high-temperature prevention construction and flood prevention and typhoon prevention?

1. Project Overview

Project Name: Zhoushan Jiawen International Hotel Project

Construction Unit: Zhoushan Hongsheng Real Estate Co., Ltd.

Design Unit: Zhoushan Planning and Architectural Design Institute

Survey unit: Zhejiang Huaxia Engineering Survey Institute

Construction unit: Zhejiang Qiandao Construction Co., Ltd.

2. Safety The main basis for construction supervision

1) The Production Safety Law of the People's Republic of China and the State.

2) Construction Project Safety Production Management Regulations.

3) Regulations on production safety issued by construction administrative departments at all levels.

4) Mandatory provisions of the national engineering construction standards for house construction (Title 9 Construction Safety) at the end of 2002

3. Tasks of safety construction supervision

Construction The main task of stage safety supervision is to, based on the above-mentioned main basis for safety construction supervision, the project supervision department inspect and urge the construction party to strictly implement the relevant laws, regulations, rules, norms, procedures and standards for safety production, and formulate various practical safety production Rules and regulations. Implement various safety technical measures and organizational measures at the construction site to prevent the occurrence of safety accidents, achieve safe construction, and complete construction tasks with quality and quantity.

IV. Main tasks of high temperature prevention, flood prevention and typhoon prevention supervision

1. The summer and autumn seasons have entered a period of high temperatures and typhoons. The project supervision department should strengthen daily safety supervision work and supervise Construction units carefully carry out various safety production tasks during construction in summer and autumn to prevent safety accidents and losses caused by high-temperature construction and typhoons.

2. For high-temperature construction, the construction units are urged to attach great importance to heatstroke prevention and cooling. During high-temperature periods, reasonably arrange the work and rest time on the construction site, avoid construction during high-temperature periods, provide sufficient heatstroke prevention and cooling drugs, and prohibit people with poor physical condition from working on the job. If someone suffers from heat stroke, people with certain professional rescue knowledge should be immediately organized Carry out rescue.

3. Supervise the construction unit to prepare an emergency rescue plan and set up an emergency rescue team in the project department to ensure that there are certain personnel who can immediately carry out emergency rescue work when an accident occurs to reduce losses. All functional personnel of the rescue team should receive corresponding training.

4. Supervise construction units to equip sufficient fire-fighting equipment, communication equipment for external communication, trained firefighters and other functional personnel, corresponding medical rescue equipment, backup lighting equipment, and sufficient funds. The regional plan indicating flood control, fire-fighting equipment layout points, and safety passages shall be posted in a conspicuous location. External contact numbers: 119 for fire, 120 for first aid, and 121 for weather. They must also be marked on the area plan.

5. Supervise the project department to inspect once a month to ensure the integrity of flood control and fire-fighting equipment and to perform reasonable maintenance.

6. Supervise the project department’s liaison team to pay attention to the weather forecast during the typhoon-prone season. If there is a typhoon or heavy rain, an emergency notice must be issued. Construction must be stopped for typhoons above level 6, and emergency precautions must be entered for typhoons above level 8. Prepare for typhoons and heavy rains.

7. Before the arrival of typhoons and heavy rains, urge the project department’s typhoon and rainstorm prevention leadership team and typhoon and rainstorm prevention functional teams to be prepared for typhoons and heavy rains: dust-prone materials on site should be covered, and dust-prone materials on site should be covered. Materials blown away by the wind should be collected and fixed; the scaffolding should be reinforced and no objects should be placed on the scaffolding; check the smoothness of the water discharge pipes and remove easy-to-clog objects; the surrounding environment should be cleared; mobile houses, mechanical equipment protection sheds, and tower crane derricks should be For reinforcement, if the tower crane head can be put down, if it cannot be put down, the head should be placed with the wind, and the brake in the direction of rotation should be released; the power supply at the construction site should be cut off, and backup lighting equipment should be prepared.

8. Supervise the area where the project department is located to keep fire escapes and safety passages open. Office doors and windows should be closed. Communication between typhoon and rainstorm prevention leadership groups and typhoon and rainstorm prevention functional teams at all levels must be smooth.

9. After typhoons and heavy rains occur, the typhoon and heavy rain prevention leading group launches emergency plans for typhoon and heavy rain prevention.

The personnel on duty must enter an emergency state, inspect the surrounding conditions of the site, and report any abnormalities to the leadership team in a timely manner.

10. When a typhoon causes a fire, the typhoon prevention and rescue team should immediately organize a firefighting and report to the leadership group to initiate a fire prevention emergency plan.

11. If there is a collapse accident caused by a typhoon and people are trapped, the evacuation team will determine the evacuation and escape routes according to the on-site conditions, organize the escape and evacuation, and be responsible for maintaining order and counting the number of people. If someone is injured, the rescue team should immediately organize rescue and report to the leading group to initiate an emergency plan for accidental injury. If heavy rain causes blockage of water discharge pipes or environmental pollution, the environmental protection team should immediately organize dredging and control. If there are materials that need to be rescued, the damage control team should immediately organize material rescue and control losses. The environmental protection team is responsible for taking measures to control environmental pollution.

12. The typhoon and heavy rain prevention leading group shall be responsible for on-site command, rescue, communication, and vehicle use and dispatch.

13. Accidents caused by typhoons and heavy rains should be reported immediately to the on-duty personnel of the superior department to facilitate coordination. Correction and Improvement After the occurrence of typhoons and heavy rains, the Safety Department is responsible for evaluating and improving emergency plans.

I believe that after the above introduction, everyone has a certain understanding of the implementation details of special supervision for high-temperature prevention construction and flood prevention and typhoon prevention. Welcome to log in to Zhongda Consulting for more relevant information.