Work arrangement and decoration process of hotel decoration approach

The preparatory stage of the whole process of hotel decoration

1, the blue prints.the design

The decoration of star-rated hotels is different from ordinary decoration, and must comply with the decoration regulations of star-rated hotels of the National Tourism Administration. The success of star-rated hotels lies in two aspects; One is hardware and the other is software. Hardware is decoration and equipment installation, which is directly related to the future operating costs of the hotel. Owners, managers of relevant departments of hotel management companies, relevant personnel and designers, etc. Design drawings should be made to determine whether the functional layout of the hotel is reasonable and meets the requirements of star-rated hotels. Whether it is in line with the normal business and energy saving of future star-rated hotels, whether it is in line with water supply and drainage, whether the pipeline layout is reasonable, whether it is convenient for future metering in various regions, whether the living pool meets the requirements of star-rated hotels and whether it is convenient for maintenance. Whether the power of electric transformer is enough, whether the power of distribution box is enough, whether it is convenient for future measurement in various regions, and whether the layout of lamps meets the requirements of future energy saving. Whether the functional layout of weak current telephone and network cable is reasonable, and whether the voice control equipment meets the needs of meetings and banquets in star-rated hotels. Whether the layout of air conditioning functions is reasonable, whether the fresh air volume is reasonable, whether the noise exceeds the standard, and whether the air conditioning power is sufficient. The fire control function must be determined by local fire control audit, fire protection zoning, smoke control, spraying and smoke detection. , it is necessary to conform to the specifications, but also to conform to the decoration effect. The functional layout of kitchen equipment is to determine the kitchen area according to the number of people dining; Whether the air supply volume and exhaust volume meet the standards and whether the smoke exhaust noise exceeds the standard.

2. Bidding by system or type of work

The system includes: external wall, water, electricity, weak current, fire protection, HVAC, elevator, decoration, kitchen equipment, conference equipment, etc.

3. Go through the relevant construction permit procedures, and send the elevation renderings to the Urban Planning Bureau for examination and approval, and send the interior decoration drawings to the fire department for examination and approval, and carry out the decoration construction according to the fire acceptance opinions. The smoke exhaust and drainage drawings of boilers and kitchens shall be submitted to the Environmental Protection Bureau for approval, and the local construction bureau shall handle the decoration construction permit. Go through the formalities of temporary electricity and water use on the construction site. Decoration execution stage.

A, material approach acceptance:

1, strictly control the quality of material acceptance. The main materials shall have the qualification certificate, ex-factory quality certificate, certificate of approval and instructions of the supplier or processing unit. Must meet the requirements of fire protection and environmental protection.

2. Check whether all materials are consistent with the signed contract.

3. Check whether the thickness and flatness of the blockboard meet the requirements, and fill in the acceptance record. 4. Check whether the veneer thickness and color difference meet the requirements, and fill in the acceptance record. 5. Check whether the thickness of gypsum board meets the requirements and fill in the acceptance record. 6. Check whether the cement meets the design requirements and fill in the acceptance record. 7. Check whether the color difference of wallpaper meets the requirements and fill in the acceptance record. 8. Check whether the color difference of marble meets the requirements and fill in the acceptance record.

9. Check whether all ceiling materials meet the design or contract requirements and fill in the acceptance record 10, check whether all pipes meet the design or contract requirements and fill in the acceptance record 1 1, check whether all wires meet the design or contract requirements and fill in the acceptance record 12, and check whether all hardware and sanitary wares meet the design or contract requirements and fill in the acceptance record. Check whether all equipment meets the design or contract requirements and fill in the acceptance record 14, check whether all furniture meets the design or contract requirements and fill in the acceptance record 15, and check whether all electrical appliances meet the design or contract requirements and fill in the acceptance record. All materials should be filed. Attachment material acceptance form:

Second, the site management:

1. Work out the construction project schedule (external wall, water, electricity, fire protection, heating and ventilation, decoration) together with the winning bidder or team.

2. Sign the following responsibility letters with relevant construction team leaders and file these materials: a. On-site electricity safety responsibility letter b. On-site fire safety responsibility letter c. On-site civilized construction responsibility letter d. On-site construction personnel personal safety responsibility letter.

3. Hold a coordination meeting for the construction team leader every day, coordinate the problems between the construction teams in time, solve the problems in time, and require the site garbage to be cleared.

4, by the company's security management personnel, on duty 24 hours a day, regularly patrol the site, found that the construction team has illegal situation to stop in time, to register the site construction personnel and issue a pass; Register the people who go in and out of the construction site without a pass, and the safety management personnel must check all the items carried by the people who go out. Take-away tools must be signed and approved by the construction personnel of Party A and Party B before being released.

5. Check the site progress against the site construction schedule every day;

6, patrol the construction team every day, check whether the construction is in line with national standards, and open a rectification contact list for irregular places to order the construction team to rectify;

7. If the site construction is not in conformity with the drawings, timely adjust or contact the design unit according to the site conditions, so as not to affect the construction period.

8, according to the national construction specification for daily inspection of the site.

Check whether the suspended ceiling works conform to the suspender distance 1 1m, main dragon distance 1 1m, secondary dragon distance 4545cm, gypsum board joint distance 0.3-05cm, and the distance between gypsum board fixing screws and half.