A hotel construction organization design scheme?

What is the specific content of a hotel construction organization design scheme? Zhong Da Consulting will answer your questions below.

One. Project overview

This project is invested by XXX Hotel and designed by Nanhai XXX Design Co., Ltd. The total construction period is 65,438+005 calendar days, and all civil works and some installation works are required to be completed and accepted.

(a) Brief architectural design:

Taoyuan Yu Yu multifunction hall

The building is 15.00 meters long from east to west and 28.000 meters wide from north to south. There are two floors in total, one is the storage room (the ground elevation is -2. 150M), the other is the multi-function hall and ancillary facilities (the elevation is 0.000), and the mezzanine is the control room. The building area is1060m2.

Taoyuan Yu Yu collective dormitory

The building is in the shape of a mountain, with a length of 29.500 meters from east to west. It has two floors, one is the dormitory and various offices and conference rooms, and the other is the dormitory.

(2) Structural design:

Taoyuan Yu Yu multifunction hall

The engineering foundation adopts natural foundation, two-story frame structure and prestressed beamless floor. The maximum span is 8.0 meters.

Taoyuan Yu Yu collective dormitory

The engineering foundation adopts natural foundation with two layers of frame structure.

Second, the construction deployment:

(1). Structure diagram

Taoyuan Yu Yu multifunction hall

1, the foundation excavation and foundation works are planned to be completed in 15.

2. The main frame (including masonry structure and prestressed construction) will be completed within 45 days. When the progress reaches the first column, the grid must be erected and steel suspenders installed.

3, after the completion of the roof floor, began to interspersed with ceiling plastering, bricklaying team can enter the scene five days later.

4, after the completion of the main project, can enter the exterior wall decoration construction, followed by the ground decoration project, sewage pipe installation project can enter the construction site.

5, five days after the completion of the exterior wall decoration project, immediately remove the grille and hanging cage; Party A shall carry out water and electricity installation, and the water and electricity installation period shall be 70 days. General construction schedule (see attached table)

Taoyuan Yu Yu collective dormitory

1, it is planned to complete the foundation excavation and foundation works (pile caps and ground beams to 0.000) within 15 days.

2. The main frame will be completed within 25 days. When the progress reaches the first column, the grid must be erected and steel suspenders installed.

3, after the completion of the roof floor, began to interspersed with ceiling plastering, bricklaying team can enter the scene five days later.

4. After the completion of the main bricklaying project, you can enter the external wall decoration construction, followed by the ground decoration project and the sewage pipe installation project.

5, five days after the completion of the exterior wall decoration project, immediately remove the grille and hanging cage; Party A shall carry out water and electricity installation, and the water and electricity installation period shall be 75 days. Overall construction schedule.