Traditional Culture Encyclopedia - Hotel franchise - Construction organization design of a hotel decoration project in Jiangsu?

Construction organization design of a hotel decoration project in Jiangsu?

What is the specific content of the construction organization design of a hotel decoration project in Jiangsu? Zhong Da Consulting will answer your questions below.

Chapter I Construction Organization Design

Section 1

1- 1 number range

The following areas of XXX Hotel in Jiangsu Province

1, semi-basement, all interior decoration on the first floor, including spiral staircase and elevator hall.

2, all exterior wall decoration, roof, parking lot.

3. Semi-basement, first floor, sightseeing elevator curtain wall, lighting ceiling, main entrance shed and awning outside the restaurant.

4. All of Area I (decoration where axis 1-8 intersects with axis H-K)

Compilation basis of 1-2

1, XXX hotel building decoration bidding documents and instructions, bill of quantities and answering documents.

2. Construction drawing of indoor and outdoor decoration design of XX Hotel designed by Shenzhen XX.

3 national, provincial and municipal current construction and acceptance specifications and quality inspection evaluation standards.

Code for Construction and Acceptance of Building Decoration Engineering (JGJ73-9 1)

Code for construction and acceptance of building installation engineering

Code for fire protection design of interior decoration of buildings (GB-50022-95)

Natural granite stone building board (JC-205)

Technical specification for glass curtain wall engineering (JGJ 102-96)

Technical specification for stone and metal curtain wall engineering (discussion draft)

Building curtain wall (JG3035- 1996)

Technical Code for Safety of Building Engineering (JGJ80-9 1)

Technical Code for Safety of Temporary Building Electricity in Construction Site (JCJ46-88)

4, the promotion of new technologies, new processes and new materials.

5. Shenzhen XX Decoration Engineering Company ISO900 1 quality management system standard program documents and supporting documents.

6. Field investigation.

Compilation point of 1-3

1, this decoration project must meet the standard requirements of a four-star hotel. The decoration project of this bid section is the focus of the whole hotel decoration. Mastering the main construction methods and technical measures, preventing common quality defects and ensuring the engineering quality to reach the provincial excellent standard are the key points of the decoration construction scheme of this project.

2. The decoration engineering of this bid section has high technical requirements and tight construction period. The key points of this decoration project construction plan are to carefully study the progress plan, reasonably arrange the process interspersed, grasp the total construction period, control the total progress, and implement the phased plan to ensure that the construction period is completed ahead of schedule.

3. The management of the whole construction process of the decoration project in this bid section, reasonable site layout, strict facade protection, cross construction, flow operation, safe electricity consumption, mechanical equipment, site fire prevention, site civilization and environmental pollution, and ensuring safe production and civilized construction are important components of the decoration project construction scheme.

4. In order to achieve the (above) expected goal of decoration engineering construction, the organizational structure of the project department, the composition of the project department, the preparation of resources, the determination of technical scheme, the implementation of plan, the implementation of measures, the perfection of system, the management in place and the tacit understanding of cooperation are the important guarantees for the quality, time limit, safety and civilized construction of decoration engineering, and also the key points of studying the construction scheme of decoration engineering. Thank you very much for inviting our company to participate in the bidding for the renovation (expansion) project of XXX Hotel. If we are lucky enough to win the bid, we will further consult the owner, design and supervision engineer with an open mind. This decoration construction plan will be supplemented and modified in detail during the construction, and as a guide, the construction will be carefully organized, and the inspection and supervision of the superior and local competent departments at all levels will be seriously accepted, and the owner will be fully responsible for the project quality, construction period and safety.