Traditional Culture Encyclopedia - Hotel reservation - How to construct the hotel lobby driveway?

How to construct the hotel lobby driveway?

Construction steps of hotel lobby driveway.

1. Ground treatment of hotel lobby: It shall be arranged, compacted and leveled to reach the specified compaction density, and concrete of the same color and mold shall be poured in the construction area and leveled with tools. Drainage gradient should be considered to avoid water accumulation.

2. Before the initial setting of concrete, the concrete shall be leveled with a trowel, and the lobby driveway shall be evenly spread on the concrete surface in two or three times according to the prescribed dosage by paving method, and the concrete shall be leveled and polished with a trowel every time.

3, according to the prescribed dosage will release agent evenly on the concrete surface, that is, complete.