What is the installation method of marble door cover?
Construction preparation work
Material requirements: cement: No.325 ordinary portland cement, white cement: No.325 white cement; Sand: coarse sand or medium sand, screened before use; Stone: Prepare the materials according to the specifications and colors required by the design and drawings, and the surface is free of hidden damage, weathering and other defects; Other materials: such as plaster of Paris, copper wire or galvanized lead wire, lead skin, hard plastic strips and supporting pendants; With a proper amount of stone slag and mineral pigments close to the color of marble or polished granite and prefabricated terrazzo; 107 glue and special plastic hose for filling gaps in veneer, etc.
construction sequence
Glue brushing: when the base is wet, first brush a layer of 107 glue mud (107 glue mixture 10% water) and use the brush as the base; The bottom ash is made of 1: 3 cement mortar with a thickness of about 12mm, which is operated twice. After the bottom ash is compacted and leveled, scrape the bottom ash surface.
Drilling and slotting
Before installation, drill holes on the decorative board with bench drill according to the design requirements. Nail the wooden frame in advance, let the drill directly face the upper end face of each panel, and drill holes on the upper and lower sides of each panel. The holes are located at 1/4 at both ends of the panel width, and two holes are drilled on each face.
Binding steel mesh
First, the embedded steel bars on the wall are removed, and the parts of the wall are cleaned with marble or prefabricated terrazzo. Bending and pressing the tied vertical bars on the wall with embedded steel bars. Transverse reinforcement is bound marble or precast terrazzo and polished granite slab.
Broken line
First of all, marble or precast terrazzo, polished granite walls, cylinders, doors and windows should be hung with big lines from top to bottom to find out the verticality. The thickness of marble or precast terrazzo, polished granite slab, the gap between mortar pouring and the size of steel mesh should be considered.
fixed
Take the slate according to the position, straighten the copper wire or galvanized lead wire, put the slate in place, and tie the copper wire or galvanized lead wire at the lower mouth of the slate to the transverse bar. The cylinder can be installed clockwise, usually starting from the front. After the first floor is installed, use a ruler to find the verticality. After finding out the verticality, flatness and verticality, prepare the cooked gypsum with a bowl, and paste the gypsum made into porridge on marble or prefabricated terrazzo and polished granite board to make the two layers of slate integrated.
The above are the construction steps of the marble door cover, because the door cover is generally very high, so the installation effect is very important. If the installation is not firm, it will not only affect the effect of the door, but also easily fall off. Because the area of marble door cover is relatively small, a reasonable installation process is very important. Marble door covers are generally installed by professional workers. The service life is determined by the fineness of installation, so every working procedure should be carefully marked and checked to ensure the construction quality.
- Previous article:Price of ceiling materials for interior decoration
- Next article:Where is a good place to shop in Kunming?
- Related articles
- What are the main courses of western food?
- Which hotel in Qingdao cooks delicious fish?
- Recommended hot spring hotels around Jiangsu, Zhejiang and Shanghai
- Is it shameful to learn to cook after graduating from college?
- Why is Thailand an unsafe country?
- What are the top ten majors with the best employment prospects in the future?
- Announcement on the recruitment of 120 teachers for public institutions in Gaotang County, Liaocheng, Shandong in 2014
- What is the telephone number of Heyuan Bavarian Manor Marketing Center?
- What does it mean to hang yourself?
- Where to scan the QR code to rent a car in Guilin?