Traditional Culture Encyclopedia - Photography major - What are the detailed rules for the implementation of special supervision for high-temperature construction, flood control and typhoon prevention?

What are the detailed rules for the implementation of special supervision for high-temperature construction, flood control and typhoon prevention?

I. Overview of the Project

Project Name: Zhoushan Wen Jia International Hotel Project

Employer: Zhoushan Hongsheng Real Estate Co., Ltd.

Design unit: Zhoushan Planning and Architectural Design and Research Institute.

Survey unit: Zhejiang Huaxia Engineering Survey Institute.

Construction unit: Zhejiang Qiandao Construction Co., Ltd.

Second, the main basis of safety construction supervision

1) People's Republic of China (PRC) (PRC) safety production law.

2) Regulations on Safety Production Management of Construction Projects.

3) Safety production regulations issued by construction administrative departments at all levels.

4) Mandatory Provisions of National Engineering Construction Standards (Chapter 9: Construction Safety) By the end of 2002

Third, the task of safety construction supervision

The main task of safety supervision in the construction stage is to inspect and urge the construction party to strictly implement the laws, regulations, provisions, norms, procedures and standards related to safety production and formulate various feasible safety production rules and regulations according to the above-mentioned main basis of safety construction supervision. Implement various safety technical measures and organizational measures on the construction site, put an end to safety accidents, realize safe construction, and complete construction tasks with good quality and quantity.

Four, the main work of high temperature prevention, flood control and typhoon prevention supervision

1, summer and autumn have entered a period of high temperature, intense heat and frequent typhoons. The project supervision department should strengthen daily safety supervision, urge the construction unit to do a good job in safety production in summer and autumn construction, and prevent safety accidents and losses caused by high temperature construction and typhoons.

2. For high-temperature construction, urge the construction unit to attach great importance to heatstroke prevention and cooling. During the high temperature period, reasonably arrange the work and rest time of the construction site, avoid the construction during the high temperature period, equip with enough heatstroke prevention and cooling drugs, and prohibit people in poor health from working at their posts. If heatstroke occurs, immediately organize personnel with certain professional rescue knowledge to rescue.

3, urge the construction unit to prepare emergency rescue plan, and set up an emergency rescue team in the project department to ensure that there are certain personnel, once an accident occurs, emergency rescue work can be carried out immediately to reduce losses. All functional personnel of the rescue team should receive corresponding training.

4. Supervise the construction unit to be equipped with sufficient fire fighting equipment, external communication equipment, trained firefighters and other functional personnel, corresponding medical rescue equipment, standby lighting equipment and sufficient funds. And in a prominent position, post a regional plan indicating the layout of flood control and fire fighting equipment and safe passage. External telephone numbers: fire alarm 1 19, first aid 120, weather 12 1, also need to be marked on the regional plan.

5, urge the project department to check once a month, to ensure that the flood control and fire fighting equipment in good condition, and reasonable maintenance.

6. Supervise the project department to listen to the weather forecast in typhoon-prone seasons. If there is a typhoon or rainstorm, it is necessary to issue an emergency notice. Construction should be stopped for typhoons above magnitude 6, and emergency prevention and rainstorm preparation should be made for typhoons above magnitude 8.

7. Supervise the leading group for typhoon prevention and rainstorm prevention and the functional group for typhoon prevention and rainstorm prevention of the project department to prepare for typhoon prevention and rainstorm prevention: cover the materials that are easy to raise dust on site, and collect and fix the materials that are easy to be blown away by the wind; Scaffolding should be reinforced, and nothing can be put on the scaffold; Check whether the drainage pipeline of water body is unblocked and remove the easily blocked objects; The surrounding environment chores should be removed; Trailer, mechanical equipment protective shed, tower crane derrick should be reinforced, tower crane head should be put down when it can be put down, the head should be placed with the wind, and the rotary brake should be released; Power supply should be cut off at the construction site, and standby lighting equipment should be prepared.

8. Supervise and urge the area where the project department is located to keep the fire exits and safe exits unblocked. Close the doors and windows of the office. The communication between the leading institutions for typhoon prevention and rainstorm prevention at all levels and the functional teams for typhoon prevention and rainstorm prevention should be smooth.

9. After the typhoon and rainstorm, the leading group for typhoon and rainstorm prevention started the emergency plan for typhoon and rainstorm prevention.

The personnel on duty should enter the emergency state, patrol the surrounding situation of the site, and report to the leading group in time if any abnormal situation is found.

10. When a fire is caused by a typhoon, the typhoon prevention and rescue team shall immediately organize fire fighting, report to the leading group and start the fire emergency plan.

1 1. If people are trapped due to typhoon, the evacuation team will determine the evacuation and escape routes according to the site conditions, organize evacuation, and be responsible for maintaining order and counting the number of people. In case of personal injury, the rescue team should immediately organize rescue, report to the leading group and start the emergency plan for accidental injury. If the rainstorm causes blockage of drainage pipes or environmental pollution, the environmental protection group should immediately organize dredging treatment. If materials need to be rescued, the damage management team should immediately organize material rescue to control losses, and the environmental protection team is responsible for taking measures to control environmental pollution.

12. The leading group for typhoon and rainstorm prevention is responsible for on-site command, rescue, communication and vehicle dispatch.

13. Accidents caused by typhoons and rainstorms should be reported to the superior personnel on duty immediately for coordination. After typhoon and rainstorm, the Security Department is responsible for evaluating and improving the emergency plan.

I believe that after the above introduction, everyone has a certain understanding of the implementation rules for the special supervision of flood control and typhoon prevention in high temperature construction. Welcome to Zhong Da for more information.