Construction sequence:
The safety circle around the lower part of the chimney of Jiangsu Fayuan High-altitude Engineering Co., Ltd. → Open the smoke outlet 1x 1.5m → Dismantle the chimney → Dismantle the granite water film for dust removal → Clean up the site.
Third, the main construction technology:
1, 40-meter-high brick chimney and granite water film dust removal are all removed manually, and the foundation is not removed. There are safety ropes around the safety line, and special personnel patrol to protect the safety of pedestrians. Clear traffic signs should be hung on the safety rope, and red lights should be hung at night.
2. First put a safety steel pipe at the top of the chimney or climb the Chinese fir pole of the ladder at the top of the chimney, tie it firmly, and lock the safety of people on the steel pipe for construction and demolition. During construction, the top of the chimney is leveled with a 40× 250× 3000mm wooden board, so that the construction personnel can operate safely. All the bricks removed by electric pickaxe came down from the chimney. During the chimney demolition, the hammer can't be operated due to the thickening of the chimney wall, so the gear jack must be used, and the channel steel and steel pipe should be welded when the track is demolished.
If necessary, click "Consultation →→→→→→" Jiangsu Fayuan Chimney Demolition Professional Company "in this scheme.
Fourth, the construction method:
1. Before manual blasting, use vent as slag outlet, and use small excavator to slag.
2. The construction personnel stand on the scaffold, hang the safety belt on the steel pipe, and then dismantle the barrel one by one with picks and hammers from outside to inside, so that all the ballast blocks are buried in the barrel;
3. Demolition operation is strictly prohibited at night, and slag removal can be arranged at night, which is beneficial to continue demolition during the day. Blasting and slag removal are strictly prohibited at the same time;
4. Scaffolding decreases with the decrease of construction surface, but scaffolding must always be meters to meters higher than the construction surface to prevent slag from flying out of the protective layer of scaffolding;
5. Oxygen and acetylene bottles are placed on the operation platform, only the gas cutting gun is on the construction surface, and the lightning protection antenna is dismantled and burned (the truncation length is not more than meters).
Verb (abbreviation for verb) Safety measures:
1, the construction personnel should experience on schedule, always know the employees' physique and thoughts, and prevent people who are hard of hearing and have poor eyesight from participating in the construction.
2. Strive to create a good construction environment, let employees make more contributions to the project, ensure that they don't drink before going to work, don't go to work in spite of illness, work and rest on time, strictly implement safety rules and regulations, and formulate emergency plans for the project in detail.
3, the construction personnel must hold relevant certificates, implement the regulations of high-altitude suspension operation, wear protective equipment, construction approach must be carried out according to the route specified by the owner, strictly implement the safety management rules and regulations of Jinan Yuxing Chemical Co., Ltd., personnel entering the construction site must wear safety helmets, complete protective equipment, and aerial workers must wear gas masks and rubber gloves to fasten their seat belts.
- Related articles
- Ceng Fanzhi's Leopard: Misappropriation or Plagiarism?
- Who can tell me some technical terms of animation?
- Why does the mobile phone flash when taking pictures on the LED display?
- Does everyone get married with a photographer and a makeup artist? I hope you can share your experience, thank you!
- What is it about Canon that always touches Nikon?
- At KIMI's birthday party, there was a beautiful song sung by several female voices. What is this?
- When will the Beauty of Cheongsam be broadcast —— Introduction of location
- Beijing decoration design company Beijing 80 square meters decoration budget ranking.
- Employment direction of film and television photography and production specialty
- What is the appreciation of strange stones?