Flow chart for approval of bottled liquefied petroleum gas supply point

Project type: approval of administrative license

Commitment period: 8 working days

Service telephone number: 5822694 (accepting department)

Supervisory complaint telephone number: 5822576 (bureau office)

Venue: Construction Safety Supervision Station of County Urban and Rural Planning and Construction Bureau

Application materials:

1, application form for provincial bottled gas supply license;

2. Supply point labor permit;

3. Topographic map and plan of the location of the supply point;

4, fire proof, professional training certificate of employees;

5, safety management and management system, service standards and measures.

Submit application materials (including contact person and telephone number)

Acceptance of construction safety supervision station

Verification of materials and field visits

(3 working days)

Draft, put forward examination and approval opinions and report to the leaders in charge (2 working days)

Examination and approval (in charge of leaders and directors)

(3 working days)

Issue a license

Flow chart of preliminary examination of bottled liquefied petroleum gas business license

Project type: approval of administrative license

Commitment period: 8 working days

Service telephone number: (accepting department)

Telephone number of supervision complaint: (bureau office)

Venue: Construction Safety Supervision Station of County Urban and Rural Planning and Construction Bureau

Submit bottled gas

Provide license application materials

Materials to be submitted by the applicant:

1, provincial bottled gas business license application form;

2. Business license of enterprise legal person;

3. capital verification certificate. If the scale of the supply base is less than 100 cubic meters, the registered capital shall not be less than1000000 yuan; 100-200m3, not less than 1.5 million yuan; More than 200 cubic meters, not less than 2 million yuan;

4, project completion acceptance record;

5, the public security fire control institutions of building fire design audit opinions, completion acceptance opinions;

6, quality and technical supervision departments issued by the pressure vessel products on-site installation, assembly, manufacturing safety and quality supervision and inspection certificate or completion acceptance opinions;

7, to ensure a stable supply and meet the national standards of gas source certificate;

8. Employee materials (employee list, copy of ID card, labor contract, social insurance fee materials; The appointment documents of the legal representative; The appointment documents, employment contracts and professional title certificates of the technical person in charge and the safety person in charge; Copy of graduation certificate and title certificate of technical personnel; Operator gas professional training certificate);

9, enterprise management rules and regulations (including enterprise management, safety management, production safety accident emergency plan).

Acceptance of construction safety supervision station

Verification of materials and field visits

(3 working days)

Draft, put forward examination and approval opinions and report to the leaders in charge (2 working days)

Examination and approval (in charge of leaders and directors)

(3 working days)

Report to the Municipal Construction Bureau