Some schools need maintenance because of their age. What should we do at this time? The following is my school maintenance instructions, welcome to refer to!

School maintenance instructions 1:

Dear leaders of the Municipal Education Bureau:

XX Primary School is a rural boarding school after the layout adjustment of Kaili Education Bureau. The students come from a village eight kilometers away. At present, the toilets used by teachers and students are simple brick and wood toilets built in the 1980s. Due to years of disrepair, tiles are broken, eaves, rafters and purlins rot, and there is no drainage ditch behind the toilet, which leads to rain leakage on the roof and cracks on the wall and ground. In order to eliminate potential safety hazards and avoid endangering the safety of teachers and students, the school decided to paint the interior and exterior walls of toilets, replace rotten roof wood and make up broken tiles. Due to the shortage of funds, the school is in urgent need of maintenance. I implore the bureau to give a financial subsidy of 6.5438+0 million yuan to solve the urgent needs of the school.

Is it suitable? Please indicate!

XX primary school

20XX April 22nd

School maintenance instructions 2:

Zhenjiang District Science and Education Bureau:

Due to the recent severe weather such as continuous rainfall, freezing and strong wind, there are many dangerous situations in the fence of our school: 20XX1October 65438+1/day, the fence in the campus collapsed 30 meters, and the fence on the east side collapsed 60 meters. In addition, due to the subsidence of the foundation, there are many cracks in the school cultural corridor. In addition, due to historical reasons, there is no fence in the west of the sports ground, and the fence of the grain depot has been borrowed. Now it has been in disrepair for a long time, and many places have collapsed. Students enter and leave the school through gaps, which brings a lot of inconvenience to the management of the school. For the safety of teachers and students, and for the safety of the school's property, we implore the Science and Education Bureau to allocate funds urgently to help our school maintain the fence. Please indicate whether the above explanation is correct.

Meicun primary school

20xx65438+1October 13

School maintenance instructions 3:

Principal's office:

With the coming of summer vacation, in order to strengthen the continuity of school logistics management and ensure the normal start of next semester, it is decided to use the summer vacation to organize a centralized maintenance of school public facilities and class property, and at the same time start to implement a number of infrastructure projects. The specific scheme is as follows:

I. Infrastructure Engineering Group

capital construction project

1, and began to implement the greening project of the north campus.

2. Start the construction and renovation of the cement stadium.

3. Complete the maintenance of roof tiles in the first phase of the project.

4. Begin to implement campus asphalt concrete pavement reconstruction.

5. Start the construction of the "Building Skills Training Center" project.

6. Construction and relocation of the new school distribution room.

Second, the property maintenance group

Maintenance project

1. Complete the renovation of staff canteen and student canteen.

Procurement and maintenance of related equipment

2. Complete the maintenance of school public facilities (see the list for details).

3. Complete the maintenance of school water and electricity facilities.

4. Complete the maintenance of class property and desks and chairs.

5. Do a good job in the maintenance of flowers and trees in schools.

6, do a good job of campus environmental sanitation cleaning.

7. Do a good job in checking and cleaning up school assets.

8, do a good job in the maintenance of fire control facilities.

Third, some explanations.

1, the infrastructure work has completed the examination and approval procedures and is entering the bidding stage. Once the bidding is over, it will enter the construction stage immediately, and the quantities will be settled according to the final accounts.

2, canteen renovation and public facilities maintenance according to the budget submitted to the county education bureau for examination and approval, according to the actual project final accounts.

3. Temporary personnel should go to work on normal working days, complete the specified tasks, pay normal wages, have no attendance award, and obey other work arranged by the leaders.

All maintenance work should be completed before August 20th.

If there is nothing wrong with the above report, please give instructions.

xx

XXXX,XXXX,XX,XX