What are the work requirements of the project flood control team?
1. The construction unit must incorporate flood prevention work into project management, clarify the responsibilities of each department and personnel, conduct regular flood prevention safety education, and improve the flood prevention awareness and sense of responsibility of all personnel.
2. Headquarters Flood Prevention Leading Group
(1) Formulate a full-line flood prevention and emergency plan based on the actual situation of the project.
(2) Before the flood, promptly issue flood prevention work arrangement opinions to all units, and thoroughly inspect the situation of each station, material yard, prefabrication yard, river protection, and flood prevention materials and supplies reserves.
(3) Arrange the flood prevention duty, supervise and inspect the flood prevention duty status of each construction and supervision unit and the understanding of the flood situation.
(4) Contact professional meteorological and water conservancy departments to sign service agreements, and issue weather forecasts and sudden disaster forecasts to participating units in a timely manner.
(5) Implement a 24-hour duty system at the flood season headquarters. Personnel on duty must strictly abide by duty discipline, ensure smooth communication 24 hours a day, ensure timely reporting of various flood prevention information and rapid transmission of various instructions; keep records on duty, conscientiously perform their job responsibilities, and upload and issue relevant matters in a timely manner.
3. Flood Prevention Team of the Director’s Office
(1) Accept the unified deployment of the flood prevention leading group of the headquarters, supervise and inspect the flood prevention work of the supervision and construction units, and arrange for duty during the flood season .
(2) Before the flood, thoroughly inspect the situation of each station, material yard, prefabrication yard, river protection, and flood prevention materials and supplies reserves.
IV. Flood Prevention Team of the Resident Office
(1) Before the flood, according to the unified deployment of the flood prevention leading group, supervise and inspect the flood prevention work of the construction unit, and arrange duty during the flood season.
(2) The local water conservancy department and local villagers should learn more about the rainy season, rainfall, flood season, and flood levels over the years, and formulate a flood prevention plan that can not only save project costs but also ensure safety and reliability.
(3) The resident office should be located in a place that is not easily affected by water damage. Locations that may be affected by water damage should be protected in advance and drainage facilities should be provided to ensure the safety of the site.
5. Flood prevention implementation team of the construction unit
(1) Establish a flood prevention and rescue implementation team to be responsible for directing flood prevention and rescue work within the construction jurisdiction.
(2) The local water conservancy department and local villagers should learn more about the rainy season, rainfall, flood season, and flood levels over the years, and formulate a flood prevention plan that can save project costs and ensure safety.
(3) Formulate a specific and highly targeted flood prevention and rescue emergency plan, and make reasonable arrangements and clear division of labor for rescue materials, equipment, transportation tools, manpower, etc. There must also be clear plans and detailed arrangements for emergency rescue measures. Once a danger occurs, it is necessary to ensure that the disaster relief work is carried out quickly, the plan is thorough, the measures are effective, and the materials are in place, so as to improve the ability to deal with emergencies.
(4) A flood prevention emergency drill should be held every year before the flood season to test, improve and strengthen emergency preparedness and emergency response capabilities.
(5) Before the flood season, the weak links such as bridge pile foundation construction, beam and plate prefabrication, material stacking, migrant workers' residences, and temporary drainage facilities that affect flood control should be the focus of control and investigation. Deal with hidden dangers promptly when discovered. If there are serious safety hazards, they should be reported to the headquarters immediately.
(6) The construction unit should be located in a place that is not easily affected by water damage. Locations that may be affected by water damage should be protected in advance and drainage facilities should be provided to ensure the safety of the site.
(7) When arranging the construction of cross-river bridges, the construction unit must arrange the construction of the lower part of the project during the dry season. When constructing bridges in low-lying and ravine areas, prevention of flash floods must be the focus.
(8) The construction unit must reserve necessary flood prevention materials in advance, improve flood prevention and emergency plans, and ensure safety during the flood season.
(9) The construction unit’s material yard, machinery parking location, equipment installation, etc. should avoid locations susceptible to water damage or be located in locations that are easy to evacuate. At the same time, reinforcement and protective facilities must be made to ensure the safety of materials and mechanical equipment.
(10) The construction unit should listen to and watch the weather forecast issued by the professional meteorological department in a timely manner, keep abreast of weather changes, prepare in advance, and make arrangements as early as possible to be prepared.
(11) The construction unit must prepare sufficient flood control materials and tools, such as woven bags, stones, water pumps, colored cloth, linoleum felt, water pipes, shovels, square logs, etc., for emergency use.
(12) The construction unit must regularly inspect and dredge the drainage around the station, access road, material yard, and explosive depot to ensure smooth drainage.
(13) The construction unit must regularly inspect the construction access roads and temporary drainage facilities at the construction site, strengthen management and protection, and ensure the safety and smoothness of drainage and rescue channels during flood season.
(14) The construction unit should strengthen the protection of the rivers within the jurisdiction and thoroughly dredge them to ensure smooth flow of water. Before the flood, the cleaning work of construction waste and slag in the river channel should be completed to restore the flood discharge capacity of the river channel.
For more information about engineering/service/purchasing tender document writing and production to improve the bid winning rate, you can click on the official website customer service at the bottom for free consultation: /#/?source=bdzd
- Related articles
- The weather in Shanxi in June is 5438+ 10.
- Analysis of the Most Oolong Constellation Matching
- What is the origin of the western "dragon"
- Main reasons for wide sea ice range and thick ice layer in Liaodong Bay
- Where is Yancheng, Jiangsu?
- Weather forecast in eastern Huizhou
- Weather hot oxygen
- What are the specialties and taboos when visiting graves during Qingming Festival? What are the specialties and taboos when visiting graves during Qingming Festival?
- Sentences describing the heat in midsummer in July
- rainy season