Three-prevention safety emergency plan for construction site in rainy season

In school or society, unexpected accidents sometimes occur. In order to avoid making things worse, it is necessary to prepare a specific, detailed and targeted emergency plan in advance. So what problems should be paid attention to when preparing an emergency plan? The following is the emergency plan for three defenses in rainy season on the construction site, which I collected for your reference only, hoping to help you.

Emergency Plan for Three Preventions in rainy season on construction site 1

I. General Provisions

1. Purpose of compilation

This plan is formulated in order to do a good job in flood control in the company's coal mines, improve the ability to respond quickly to major disasters and accidents caused by rainy season, prevent disasters from expanding further, and protect employees' personal safety, collective property from losses and the safe operation of all units.

2. The compilation basis is

National Guidelines for Preparing Emergency Plans, Flood Control Law, Water Law, Flood Control Regulations, National Overall Emergency Plan for Sudden Public Events, National Emergency Plan for Flood Control and Drought Relief, etc.

3. Scope of application

This Plan is applicable to the prevention and disposal of disasters such as floods, waterlogging caused by rainstorm and water accumulation in subsidence areas caused by natural or man-made factors in the company's coal mining enterprises.

4. Working principles

This Pre-plan fully embodies the people-oriented, prevention-oriented, robbery-proof combination, the idea of combining engineering and non-engineering measures, and the principles of administrative leadership responsibility system, unified command, unified dispatch, division of labor and cooperation, doing their own jobs, doing their best to rescue and ensuring safety.

II. Key protection targets

All business personnel of the company; Company's coal mine industrial square, underground engineering, underground production system equipment, ground mining area roads, ground mining area high-voltage power supply lines, ground and underground communication systems; The ground facilities of each business unit of the company, etc.

iii. emergency rescue organization and responsibilities

1. organization

the company established the "three defenses" emergency rescue headquarters in rainy season, which is located in the dispatching center.

Chief Commander: Chairman Zhang Yong

Deputy Chief Commander: Qiu Jiagui, Deputy Production Manager, Tan Jincheng, Deputy Safety Manager, and Ke Yueheng, Chief Engineer.

member units: dispatching center, geological survey department, safety supervision department, mechanical and electrical supply department, one ventilation and three prevention department, coal mining team, administrative office, monitoring room, trade union, discipline inspection office, security department, logistics department and infirmary.

Director: Director of the Dispatching Center

2. Responsibilities

Headquarters: It is mainly responsible for coordinating the operation of various departments during the emergency rescue of accidents, making overall arrangements for various emergency rescue actions, providing various information support for on-site emergency rescue, and quickly and accurately formulating disaster relief implementation plans.

commander-in-chief: fully responsible for the organization and command of flood control emergency response.

deputy commander-in-chief: assist in the organization and rescue of flood control emergency response.

member units: obey the instructions of the commander-in-chief and deputy commander-in-chief and complete all tasks assigned. Specifically:

(1) Dispatching Center: responsible for summarizing weather forecast, transmitting flood season information, arranging duty in flood season, organizing, coordinating and checking the progress of key projects of "Three Preventions" and reports on "Three Preventions". Responsible for organizing on-site emergency rescue and rescue operations according to the emergency plan, obeying the command of the headquarters, and being responsible for contacting the nearby mine rescue team for help.

(2) Geological Survey Department: responsible for hydrological observation above and below the well, regular observation of surface rivers, accumulated water and cracks in coal mining subsidence areas, arrangement of waterproof works, organization of "three-prevention" inspection, and well prevention and control of water in flood season. Be responsible for the prediction of waterproof and drainage in various mining and excavation faces underground. Responsible for providing technical data such as geological parameters of water inrush points related to each coal mine and providing technical guidance.

(3) Safety Supervision Department: responsible for supervising and inspecting the progress of "Three Preventions" in all units (focusing on coal mines). Supervise and inspect all construction units to do a good job in the "three defenses" and the excavation of ground drains, the maintenance of leaking houses, and the construction of waterproof projects. Responsible for the inspection of water accumulation in the wind wellhead and underground ventilation roadway. Be responsible for supervising the implementation of accident rescue plan and safety measures, and organizing or assisting the investigation of accidents.

(4) electromechanical supply department: responsible for the "three defenses" of the above-ground and below-ground power supply systems. Set up and test all kinds of lightning protection facilities, measure the efficiency of underground electromechanical equipment and drainage equipment, ensure that the drainage system can run at full load, and report all kinds of test results to the "Three Preventions" office of the company in time.

(5) One ventilation and three prevention departments: responsible for ventilation in coal mines and providing ventilation guarantee for accident rescue sites.

(6) Coal mining team: responsible for organizing the excavation of underground water bins and drainage ditches and the waterproof and drainage work of the waste dump system.

(7) administrative office: responsible for the timely delivery of "three defenses" documents and the arrangement of emergency vehicles.

(8) monitoring room: responsible for the "three defenses" of communication facilities to ensure smooth communication lines in flood season.

(9) Trade union: assist the accident unit to do a good job in the aftermath of the accident casualties.

(1) Discipline Inspection Office: Participate in accident investigation and accountability.

(11) security department: responsible for setting up the "three defenses" rescue team and conducting training and drills. Responsible for ensuring the smooth roads for the transportation of emergency relief materials and the public security at the accident site.

(12) logistics department: responsible for the maintenance and demolition of dangerous buildings, the "three defenses" of buildings within its jurisdiction and the resettlement of people affected by accidents. Responsible for organizing the storage of "three defenses" emergency materials and the "three defenses" work of the warehouse. It is required that the emergency materials can meet the emergency needs and be put in special warehouses.

(13) infirmary: responsible for organizing medical staff to give first aid to the injured.

(14) field headquarters: after the accident, the field headquarters is set up, and the executive deputy manager is responsible for organizing the formulation of rescue plans and field rescue work.

iv. prevention, early warning and rescue

1. preparation for prevention and early warning

every year at the beginning of April in the Gregorian calendar, all units set up the "Three Preventions" leading body to clarify their responsibilities, implement their responsibilities, report the "Three Preventions" project plan, implement the project funds, identify the responsible person, and formulate the "Three Preventions" emergency plan, so that all work is ready before the rainy season comes. In order to do a solid and effective job in flood control, it is necessary to conduct a comprehensive inspection of the "three defenses" facilities after each rain, handle hidden dangers in time, and report relevant information to the company's dispatching center regularly.

the dispatching center must collect the information released by meteorological stations every day during flood control; The safety supervision department of the company shall inspect the flood control and drainage works after heavy rain every time, and notify the dispatching center in time if any danger is found. The mine dispatching room is responsible for submitting the relevant information of "Three Preventions" work in rainy season to the dispatching center of the company, and the submission time is on the 3rd, 13th and 23rd of each month (timely report in special circumstances), and the submitted information and materials are uniformly printed on A4 paper.

2. Danger classification

-1. For general danger, the dispatching center will notify the "Three Preventions" office in rainy season, and the "Three Preventions" office will organize relevant units to visit the site and formulate rectification and preventive measures.

(2) When a major danger affects the normal operation of local production systems, the dispatching center shall notify the leaders on duty, the chief engineer and the "Three Preventions" office, and mobilize teams to carry out emergency rescue and disaster relief according to the instructions of the chief engineer.

(3) When a major danger affects the normal production or operation of each unit and the life safety of employees, the dispatching center shall notify relevant personnel to come to the dispatching center for standby in time according to the list of major accident notification units and personnel, and quickly set up a rescue and relief headquarters.

3. Rescue procedures in case of major or serious danger

(1) Receiving the police and starting the emergency.

after the "three-prevention" accident in rainy season, it must be reported in the order of "accident site person or insider-mine dispatching room-mine duty leader-mine manager, chief engineer-company dispatching center-emergency rescue headquarters", including the time, place, personnel, scope and degree of the accident. After the commander-in-chief decided to start the emergency plan for the rainy season, he immediately issued an order to start the plan to the dispatching center. Report by telephone.

(2) rescue operations.

a. after receiving the command from the commander-in-chief, the dispatching center shall notify the members of the headquarters to meet at the dispatching center according to the "telephone notification sequence of major safety accidents" in the company's emergency plan.

B, after arriving at the dispatching center, the members of the headquarters immediately go to the scene of the accident according to the instructions of the commander-in-chief or deputy commander, and set up the on-site emergency rescue and disaster relief command center to assist the accident unit to carry out emergency rescue and disaster relief work.

C, the emergency command center should formulate rescue plans and safety technical measures according to the situation of the disaster area, and organize emergency rescue. When rescuing people in distress, rescuers should determine the position, water inflow, degree of flooding, roadway damage and ventilation of the people in distress.

D, in the process of drainage, cut off the power supply, keep ventilation, strengthen the detection of toxic gases, and pay attention to the observation of roadway conditions to prevent roof caving. The professional rescue team should immediately rescue the injured and trapped personnel according to the accident scene.

E, the medical rescue team composed of medical staff should provide emergency medical treatment for the injured. When the medical rescue team cannot be treated, the injured should be transferred to the hospital for treatment in time.

F, when this plan can't meet the effective disaster relief on site, the headquarters should ask the higher authorities and government departments for help. After all the injured and trapped people are rescued, the number of people at the scene should be counted, and the rescue personnel should be evacuated from the scene of the accident. The commander-in-chief gave the order to end the emergency, and the accident rescue personnel returned to the company. The relevant departments and offices of the company will form an investigation team to investigate the accident and report to the superior.

V. Principles and procedures for restoring normal state

1. Principles for restoring normal state

(1) People-oriented principle. After the rescue at the scene of the accident, it must be verified that all casualties and people in distress in the disaster area have been rescued.

(2) the principle of ensuring safety. After the emergency rescue, conduct reconnaissance on the scene of the accident, and eliminate or control the hidden dangers that may cause another accident or induce other accidents.

(3) Implement the monitoring principle. Continuous monitoring of manual and safety instruments shall be carried out on the accident site. If any abnormal situation is found, corresponding safety technical measures shall be taken immediately to eliminate various hidden dangers.

2. Procedures for restoring normal state

After the on-site emergency rescue work is completed, the heads of all rescue working groups truthfully report the situation to the emergency rescue headquarters. After the headquarters has carefully verified that the conditions for restoring normal state have been met, the rescue team is approved to leave the scene, and the rescue work is declared to be over.

3. Post-treatment

(1) After the rescue work, the departments and units participating in the rescue should carefully check the rescue personnel and count the equipment and equipment; Accounting for rescue expenses, sorting out rescue records and drawings, and writing a rescue report within 3 days.

(2) the company organizes relevant departments to investigate the accident site, make a preliminary investigation and analysis of the accident, find out the cause of the accident, and organize the formulation of preventive measures.

(3) During the rescue process, complete emergency rescue records, plans, documents, drawings and other written and audio-visual materials should be kept.

VI. Emergency support system

1. Human resources support

Emergency response is under the unified command of the emergency rescue headquarters, and personnel from relevant departments such as ambulance, medical care and security are mobilized to organize a strong emergency rescue and relief team to ensure the effective implementation of the plan.

2. Communication (information) guarantee

The units, departments and personnel involved in the plan should ensure smooth communication and information (by telephone, fax, e-mail, etc.) and timely start of the plan.

3. Guarantee of emergency rescue materials

The logistics department should reserve "three-prevention" emergency rescue materials, and ensure that when an accident occurs, it will be put into emergency rescue work at the first time to control the disaster situation. Reserved materials must be regularly maintained to ensure normal use and managed by special personnel. No unit or individual may use it without the order of the emergency rescue headquarters. Necessary equipment should include: 1 water pumps; Large-caliber water pumps: 5 sets; All kinds of water pipes: 1 meters; Rubber tube: 1 meters; Shovel: 1; Iron wire: 3 kg; Sandbags: 1,; Loaders, excavators and engineering vehicles are on standby at any time.

4. Guarantee of funds

All units have special emergency rescue expenses, and should provide the funds needed for emergency rescue in time after the accident to ensure the smooth flow of funds needed for emergency rescue.

5. Exercises

The Security Section of each unit is responsible for organizing and implementing the "Three Preventions" emergency rescue exercise in rainy season, and reporting relevant information to the company's dispatching center and the company's safety supervision department.

VII. Training and drill of the plan

1. The safety supervision department of the company should incorporate the emergency plan for flood control into the annual training plan.

2. The Security Section of each unit should conduct drills according to the emergency plan for flood control.

3. The security department is responsible for supervising the emergency plan exercise for flood control.

VIII. Supplementary Provisions

1. Plan management and update

The company's dispatch center is responsible for the management of the plan, and makes amendments and supplements to the plan according to the problems existing in the simulation exercise. The plan update work is completed before January 1 of each year. When there is a flood accident, the headquarters will issue an order to start the corresponding emergency plan, and the production technology department, safety supervision department, mechanical and electrical supply department, ventilation and three prevention department, coal mining team, administrative office, monitoring room, trade union, discipline inspection office, security department, logistics department, infirmary and other departments of the company will be responsible for coordinating and organizing all relevant units to implement it.

2. Reward and accountability

During the implementation of the plan, the relevant units have fulfilled their duties, and the work has been done in a down-to-earth manner without any accidents, so the relevant units will be rewarded; If during the implementation of the plan, due to the negligence and poor supervision of some relevant units, resulting in human factors causing flood losses, the relevant units will be fined accordingly.

3. Plan filing

The "Three Preventions" emergency plan in rainy season is filed in the reference room of each unit.

4. Implementation time of the plan

This plan will be implemented from April 1st to October 1st. Three-prevention safety emergency plan in rainy season on construction site 2

1. General requirements for construction in rainy season

1. Ensure smooth information. Due to the uncertainty and suddenness of severe weather such as construction storm in rainy season, it is difficult to predict the degree of damage. It is necessary to strengthen the control and management of meteorological information, take effective safety measures in time and strengthen prevention.

2. comprehensiveness of protection. The construction site covers a wide range, including the safety protection of all parts of the site and temporary facilities and the safety of all personnel. Therefore, when formulating safety measures, we must be comprehensive, meticulous and thoughtful, and we must not fail to do it because of small things, so as to leave hidden dangers and bring losses.

3. Organize the construction scientifically. When compiling the construction organization design, fully consider the characteristics of construction in rainy season, arrange the projects that are not suitable for construction in rainy season in advance or later, do a good job of interspersed working procedures, improve work efficiency and construction speed, and stop construction in case of heavy storm weather.

4. Respond quickly and make emergency preparations for flood control, emergency rescue and disaster relief. During construction in rainy season, various protective measures should be further taken.