Emergency plan for typhoon prevention in chemical plant
In study, work or life, there is no guarantee that unexpected things will happen. In order to avoid more serious consequences, it is often necessary to make emergency plans in advance. So how should we prepare the emergency plan? The following is the emergency plan for typhoon prevention in chemical plants that I compiled for you, for reference only. Welcome to reading.
Emergency Plan for Typhoon Prevention in Chemical Plant 1 I. General Provisions:
1, compilation purpose
In order to do a good job of typhoon prevention, deal with all kinds of disasters caused by typhoon in time, minimize all kinds of losses on my construction site, maintain normal construction and ensure the smooth progress of the project.
2. Scope of application
This plan is applicable to the prevention and emergency treatment of typhoon disasters within the construction scope of this bid section.
3. Working principle
Typhoon disasters are managed according to the construction area, with various functional departments and construction teams as the main disposal, and each functional department is responsible for the construction team. All functional departments actively support, guide and supervise the emergency response work of corresponding construction teams. It is necessary to put the prevention of typhoon disasters in a prominent link and do a good job in various preventive work. Carefully analyze the strong winds and rainfall that may be caused by typhoons. In case of danger, respond quickly, start this emergency plan in time, and organize personnel to do their best to rescue and provide disaster relief.
4. Focus of work
(1) Waterproofing, pit wall collapse prevention and rolling stone prevention shall be carried out at the construction site of each foundation pit excavation;
(2) Prevent landslides, collapses and other disasters that may cause accidents on the construction roads;
(3) the temporary construction site and the construction team site before the disaster personnel and equipment transfer;
(4) Prepare flood control and drainage facilities for material warehouses on the construction site;
(5) Safety protection measures for vertical transportation equipment, scaffolding and construction electricity;
(6) The living guarantee of each construction site and station during the gale and heavy rain;
(7) Forecast, forecast and early warning of typhoons and rainstorms, and timely release typhoon early warning information to the construction team and the construction site.
Second, the leading group for flood control and typhoon prevention:
The project department set up a leading group for flood control and typhoon prevention with unified command, and each department was responsible for each construction team.
Leader of the leading group:
Deputy team leader:
Members:
Three. Prevention and early warning mechanism:
1, typhoon and other disasters monitoring
The safety team of the project department is responsible for the monitoring and information collection of typhoons, rainstorms, storms and mountain disasters, knowing the weather situation in advance, collecting all kinds of information on the base surface and traffic roads of each construction site in time and reporting it to the leading group.
2, the construction site safety inspection
Adhere to the safety inspection of each construction site, take the implementation of wind and flood prevention measures as the focus of inspection work, timely understand relevant information, and arrange personnel to deal with the base surface and roads that may cause harm in advance to avoid accidents when disasters occur.
3, the responsibility of the construction site early warning member to carry out.
Designate a part-time safety officer at each construction site to serve as a disaster early warning officer at the same time, mainly responsible for collecting and reporting all kinds of dynamic information at the construction site and notifying the leading group of instructions. When a disaster occurs, assist each construction team leader to implement disaster prevention measures and command.
4. Disaster early warning mechanism
The security team should establish a monitoring system for weather conditions and construction site conditions, implement information collection measures, adhere to the daily inspection system, and conduct encrypted observation and inspection in rainy season. Once dangerous signs are found, immediately call the police, transfer personnel and related equipment, and report to the leading group of the project department.
Fourth, emergency response:
The leading group of the project department is in full command, with full participation, and coordinates the participation of personnel from relevant departments.
The disaster monitoring department analyzes the development trend of typhoon according to the weather forecast, issues rainfall and wind forecast, puts forward defense targets and reports them to the leading group in time. According to the circular, the leading group made clear the defense objectives and key points, issued personnel transfer orders, declared an emergency flood control and wind prevention period, started this disaster prevention plan, sent special personnel to the affected areas to guide the work, organized and directed the rescue and relief work, reported the relevant situation to the relevant departments at higher levels in a timely manner, and reported it to the higher authorities to coordinate the deployment of medical and living materials assistance when necessary.
Verb (abbreviation for verb) for emergency rescue and disaster relief:
After the typhoon landed or was seriously affected, the disaster prevention leading group held a meeting on emergency rescue and disaster relief in time to deploy emergency rescue and disaster relief work. Organize all staff to rush to the disaster relief site, guide the rescue and devote themselves to the rescue and relief work.
(1) The team leader grasps and summarizes the disaster situation in time, coordinates the related work of emergency rescue and disaster relief, is responsible for the deployment of disaster prevention materials, completes the disaster prevention evaluation work together with relevant personnel, and reports to the construction headquarters and supervision department.
(2) According to their respective responsibilities, each team member shall organize the supply of materials and equipment needed for post-disaster recovery, and give priority to the supply of living materials for construction workers.
(3) Each construction team shall formulate the repair plan of the damaged construction site in time and organize the forces to repair it as soon as possible.
(4) The leading group should contact the local health department, organize forces to actively rescue the wounded and sick, and at the same time cooperate with government agencies to do a good job in quarantine and epidemic prevention in disaster areas to prevent the spread of the epidemic.
(5) Each construction team should organize forces to repair damaged roads and communication facilities, and do a good job in post-disaster production and self-help.
(6) Logistics personnel manage and distribute materials to ensure the supply of daily necessities.
(7) Contact the insurance department to make claims.
(8) After the typhoon, all construction teams and departments shall report the disaster to the leading group in time. After the disaster, the leading group should summarize the experience and lessons of flood fighting, disaster relief and disaster relief, and submit a written report to the engineering headquarters and supervision department.
(9) When the typhoon and disaster situation are effectively controlled, the leading group can announce the end of the emergency according to the information summary.
Six, emergency support:
1, supported by rescue team
All contractors within the scope of our project department are obliged to participate in typhoon prevention and disaster relief. Each construction team takes the team leader and safety officer as the backbone, and organizes all personnel to participate in disaster relief work when disasters occur.
2. Material safety
The Material Logistics Department should reserve necessary emergency materials for typhoon prevention for emergency use in case of major disasters.
3. Financial guarantee
Office to do a good job in the implementation of emergency rescue and disaster relief funds, when disasters occur, according to the instructions of the leading group, do a good job in the allocation and distribution of funds.
4. Communication and information security
Communication methods are mainly mobile phones and hand-held walkie-talkies. When the public telephone network breaks down, the application system of disaster prevention walkie-talkie will be started in time, and the fixed channel of notification will be used to ensure the smooth information channel.
5, medical and health security
The leading group should contact the local health department, be responsible for health and epidemic prevention and medical rescue in epidemic areas, prevent the epidemic of diseases, and do a good job in immunization and disinfection in public places.
6, typhoon relief work evaluation
After each typhoon, the leading group should summarize, analyze, qualitatively and quantitatively evaluate all aspects and links of typhoon prevention and relief work. Summarize experience, find problems, and further do a good job in preventing Taiwan from disasters.
This plan by my project department "leading group for flood control and typhoon prevention" is responsible for the interpretation.
This plan will be implemented from now on.
Emergency Plan for Typhoon Prevention in Chemical Plant 2 This plan is formulated in order to implement the spirit of Notice on Doing a Good Job in Flood Control and Typhoon Prevention issued by East China Regional Administration of Civil Aviation and the relevant requirements of local governments at all levels, in combination with the emergency plan for flood control and typhoon prevention at X Airport and the emergency plan for typhoon frontal attack at the airport.
This plan is used in conjunction with the emergency plan for flood control and typhoon prevention at X airport.
I. Working principles
In accordance with the principles of "prevention" before the arrival of a typhoon, "avoidance" when the typhoon arrives, and "rescue" after the arrival of a typhoon, the emergency response work for preventing the frontal attack of a typhoon will be carried out in an orderly manner.
Second, organization.
The emergency treatment of X airport to prevent typhoon frontal attack is carried out under the unified leadership of X airport flood control and typhoon rescue headquarters.
Third, the responsibilities of various departments.
After receiving the warning notice of typhoon attack, under the unified leadership of emergency headquarters in flood control and typhoon prevention at X Airport, all departments should act quickly and make preparations and implementation of "prevention", "avoidance" and "rescue" according to their respective responsibilities. The responsibilities of each department are as follows:
1. Airport Office: After receiving the warning notice of typhoon attack, inform the company leaders and airport departments in time. After obtaining the consent of the company leaders, start the plan, arrange personnel to be on duty, and assume the responsibilities of the X airport flood prevention and typhoon rescue headquarters office.
2. On-site command center: After receiving the typhoon attack warning and start-up plan notice, timely cooperate with the airport construction management office, maintenance support office and security inspection station to bind, reinforce or dismantle the parked aircraft and apron facilities and equipment, and timely report the relevant information to the emergency headquarters Office for Flood Control and Typhoon Prevention of X Airport.
3. Air traffic control center: after receiving the warning notice of typhoon attack, do a good job of liaison between the scheduled flight backup and the on-site flight transfer; Wind prevention, drainage and reinforcement of navigation station; Do a good job in emergency communication support; According to the requirements of the bureau, the contents of the "Airport Air Traffic Control Plan" to prevent typhoon frontal attacks were implemented.
4. Maintenance Department: After receiving the warning notice of typhoon attack, according to the requirements of the emergency plan for wind damage of the maintenance department, the parked aircraft will be parked and special vehicles will be put into storage. For special vehicles that cannot be put into storage, they should be parked far away from the parked aircraft, and brakes should be set and wheel gears should be added. The equipment and facilities on the apron should also be put into storage with windproof measures and anti-collision cones, and the traction rods and working ladders should be put into storage or fastened to prevent other facilities from being damaged by wind. This planning scheme is an emergency plan for preventing typhoon frontal attack at the airport. Strengthen the personnel on duty and keep the communication open.
5. Airport Construction Management Office: After receiving the warning notice of typhoon attack, strengthen the protection of power supply system, make preparations for emergency repair of power supply, and ensure normal power supply. Windproof measures should be taken for the equipment and facilities on the tarmac. After the gale, check the airport roads and lighting facilities immediately to prepare for the opening of the airport.
6. Security checkpoint: After receiving the warning notice of typhoon attack, reinforce and bind the covered bridge to prevent accidents.
7. Freight Center: After receiving the warning notice of typhoon attack, take windproof measures for freight equipment and facilities outside the freight warehouse, and transfer the freight equipment and facilities on the tarmac to the freight warehouse.
8. Airport Public Security Bureau: After receiving the warning notice of typhoon attack, all fire-fighting vehicles and air defense guard vehicles should be put into storage or parked downwind in time, and equipped with brakes and wheel chocks. All police officers are on standby, ready to accept the dispatch of emergency headquarters for flood control and typhoon prevention at X airport and participate in emergency rescue work.
9. Other departments: stand by at any time according to the duty requirements of the emergency plan for flood control and typhoon prevention at X airport, and keep the communication smooth.
Fourth, the job requirements
1. Responsibility in place, clear division of labor. According to the Emergency Plan for Flood Control and Typhoon Prevention at X Airport and the Emergency Plan for Typhoon Frontal Attack at X Airport, all airport departments can formulate implementation rules, define the responsible person and the specific responsible person, and decompose the typhoon prevention tasks determined in the plan to the specific responsible person, forming a horizontal and vertical work network and a flexible and efficient contact and response mechanism.
2. Full preparation and effective measures. All departments should organize experienced and capable personnel to deal with emergencies according to the typhoon prevention plan. When a strong typhoon attacks or affects the airport head-on, emergency rescue personnel should gather at the specified time to prepare for the war and arrange emergency materials, equipment and transportation. Make an emergency call at the front. Report to the Municipal Emergency Office in a timely manner and contact socialized emergency materials, equipment and tools. And make emergency preparations.
3. Strengthen vigilance and deal with it in time. The office of the flood control and typhoon rescue headquarters arranges personnel to master and develop flood dynamics, report in time when they encounter over-alert, abnormality or danger, and organize evacuation, emergency repair and reinforcement in time. In case of emergency, while reporting to the superior, we should take the initiative to take emergency measures, seize the favorable opportunity, implement emergency treatment and eliminate hidden dangers.
4. Emergency duty and smooth communication. After receiving the warning notice of typhoon attack, the office of flood control and typhoon prevention and rescue headquarters and all departments implement the 24-hour duty system to keep the information flowing. The heads of all departments and the personnel in charge of typhoon prevention in their own departments turn on their mobile phones day and night to track the rain, water, customs, disasters and secondary disasters, hold timely consultations and start relevant emergency procedures according to different situations.
Verb (abbreviation of verb) supplementary clause
1. The Airport Company is responsible for the interpretation and implementation of this scheme. And revised in time according to the actual situation.
2. This scheme shall be implemented as of the date of promulgation.
Emergency plan for typhoon prevention in chemical plants 3 I. Purpose:
Establish an emergency plan for flood prevention and typhoon rescue, strengthen the flood prevention and rescue ability of the management service area through the training and actual combat drills of emergency teams, eliminate dangerous situations more effectively and timely, reduce losses to a minimum, and ensure that the flood prevention and typhoon rescue work is foolproof.
Second, responsibilities:
The director of the management office is the commander-in-chief of flood prevention and typhoon rescue;
The person in charge of the management office is the deputy commander, who is responsible for the overall work of the equipment group;
The safety promoter is the deputy commander, responsible for the overall work of the rescue team;
The environmental organizer is the deputy commander-in-chief, responsible for the overall work of the logistics team;
The control center is responsible for the accurate transmission and coordination of information;
All off-duty personnel in the management office are emergency rescue team members for flood prevention and typhoon prevention.
Third, the division of responsibilities of the group:
3. 1 rescue team: it is composed of all the off-duty safety officers in charge of safety.
3. 1. 1 Take all measures to deal with the dangerous situation;
3. 1.2 Responsible for filling, handling and stacking flood control sandbags;
3. 1.3 use various methods to eliminate dangerous situations in time.
3. 1.4 Division of labor
3. 1.4. 1 Two off-duty central posts are responsible for loading sandbags;
3. 1.4. 2 2 No.2, No.3 and No.4 are responsible for transporting sandbags;
3. 1.4.3 Two off-duty No.6 and No.8 are responsible for piling sandbags on site and taking other measures for emergency rescue;
3. 1.4.4 The safety sponsor leads the rescue team to take all other effective methods to do all rescue work well.
3.2 Equipment group: consists of the manager of the management office and two technicians of the management office.
3.2. 1 Responsible for starting various pumps and power supply equipment;
3.2.2 Provide technical guidance to the rescue site;
3.2.3 Conduct emergency maintenance on the field equipment.
3.3 Logistics Group: It consists of environmental sponsors, domestic helpers, lifeguards, front desk attendants, cashiers and club attendants.
3.3. 1 Ensure the normal supply of all kinds of relief materials;
3.3.2 Be responsible for the rescue of the wounded on site;
3.3.3 Actively assist other groups;
3.3.4 Division of labor
3.3.4. 1 Two off-duty No.5 posts are responsible for logistics and material support;
The front desk attendants, cashiers and club attendants in 3.3.4.2 are responsible for evacuating people and rescuing the wounded, transferring the wounded to a safe place and reporting to the municipal emergency center in time;
In 3.3.4.3, lifeguards and domestic helpers are responsible for property rescue.
3.4 personnel on duty
4. 1. 1 When the personnel on duty find the danger, they shall promptly notify the center and the leaders on duty;
4. 1.2 After receiving the information, the attendant in the center shall take emergency gathering and other measures to call off-duty personnel to relieve the danger in time;
4. 1.3 The personnel on duty in the center shall immediately notify the management office manager, management office supervisor and safety director;
4. 1.4 center attendant reports to each duty post;
4. 1.5 Maintain the order of posts on site and guide personnel and vehicles;
4. 1.6 The attendant in the center should pay close attention to the site situation and seek other support when necessary.
4. 1.7 Before the typhoon comes, all posts in the management office should carefully check the potential safety hazards within their posts, eliminate the danger in time, and report the serious cases to their superiors in time.
Note: all members must obey orders, obey orders; All members should pay attention to their own safety during emergency rescue.
Emergency Plan for Typhoon Prevention in Chemical Plant 4 In order to better implement the flood prevention policy of "safety first, constant vigilance, prevention first and all-out rescue", ensure the life safety of teachers and students, strengthen the awareness of life first, make early deployment and prevention, effectively implement school safety work in flood season and ensure the life and property safety of all teachers and students, the Emergency Plan for School Safety Work in Flood Season is specially formulated.
First, prepare for safe flood season
(1) mental preparation. Give priority to prevention and establish awareness of prevention and control. Schools must put the safety of teachers and students in the first place, overcome paralysis and fluky psychology, firmly establish the concept of "everything is established in advance, and if it is not predicted, it will be abolished", and enhance the sense of urgency and responsibility for doing a good job in school flood control. We must keep a close eye on the flood season this year and do a good job in flood control at all stages and links before, during and after the flood season according to the flood control plan. It is indeed an in-depth investigation, effective rectification, careful deployment, and strict defense to ensure that all flood control measures in the school are in place.
(2) organizational preparation. Schools should establish a responsibility system for safety inspection in flood season, clarify responsibilities and tasks, and do a good job in safety inspection before the arrival of flood season. Schools should organize forces, designate special personnel to be responsible for the comprehensive and detailed inspection of school walls, drainage ditches and the surrounding environment of campus (roads and bridges), make detailed records of the inspection situation, especially hidden dangers, register and summarize them, study and formulate remediation plans, and designate specific responsible persons to implement them. According to the actual situation of the school, especially the hidden dangers, the emergency plan in flood season should be formulated in a targeted manner to ensure the practicability of the plan. The specific contents include:
1, set up a leading group for school flood prevention and rescue work, with accurate member list, post and telephone number and clear division of labor;
2, determine the flood warning and alarm methods, such as radio, whistle, etc. , and implement it to the person in charge;
3. In case of emergency, the evacuation mode, direction, route and place of students should be specific, and there should be a special person in charge;
4. Intensify publicity to let everyone know;
5, the list of personnel on duty, telephone number is accurate, to ensure unimpeded.
(3) Material preparation. According to the possible emergency rescue requirements, prepare emergency materials and equipment in advance for emergency use. To strengthen the inspection and supervision of key parts in flood season, there must be enough emergency repair force in flood season to effectively prevent emergencies in flood season.
Second, the job responsibilities
The principal is the first responsible person, and it is necessary to fully implement the school flood control work. The teaching staff of the whole school must obey the command and work arrangement of the leading group for flood control work in the school, and shall not delay the work by shirking. * * * party member should take the lead, shoulder the heavy burden bravely, play a vanguard and exemplary role, meet the urgent needs of teachers and students, unite and cooperate, help each other in the same boat, and overcome disasters. All functional groups should fully organize and assist schools and relevant departments to do a good job in emergency rescue, disaster relief and aftermath, and fulfill their duties. At the same time, we should do a good job of self-protection and strengthen self-protection measures. Anyone who does not obey the command and work arrangement, or is irresponsible, dereliction of duty, dereliction of duty and other serious consequences will be severely punished until legal responsibility is investigated.
Third, organize and lead.
In order to clarify the division of labor, strengthen leadership, unify command and coordinate operations, a leading group for school emergency rescue in flood season was established.
Team leader:
Deputy team leader:
Members:
Task: Organize the following five working groups to carry out work in time when the flood season occurs, and deploy rescue and other related work.
There are five working groups, whose composition and tasks are as follows:
(1) Emergency Rescue Team
Team leader:
Members:
Task: After the danger happens, you must rush to the scene at the first time to organize and direct the elimination and control of the danger.
(2) Rescue team
Team leader Li
Members:
Task: Responsible for contacting, coordinating and cooperating with county people's hospital, county traditional Chinese medicine hospital, county maternal and child health hospital and other hospitals, and organizing medical rescue teams to rescue the injured.
(3) Rescue and evacuation team
Team leader:
Members:
Task: Be responsible for organizing and directing the evacuation of threatened personnel and important materials on site.
(4) security team
Team leader:
Members:
Task: Contact the local police station to send police force and assist in guarding, guarding and maintaining the scene order outside the disaster site to prevent criminals from entering the scene to destroy it.
(5) Logistics Support Group
Team leader:
Members:
Task: Ensure the on-site material supply, provide necessary tools, mobilize transport vehicles, and transport rescue personnel and materials.
Fourth, emergency response.
(a) schools should strictly implement the duty post responsibility system, the establishment of school flood reporting system, in accordance with the principle of early detection, early reporting, early disposal, once found flood should immediately start the school flood emergency plan, and timely report to the county education and sports bureau.
(2) After the flood, the school office and the security office should timely and accurately collect and process the on-site information (including the situation of trapped and injured people, the materials at the flood site and the surrounding houses and facilities, the arrival of rescue teams and the demand for relief materials, etc.). ), and report to the county education and sports bureau in writing or by telephone.
Verb (short for verb) emergency support
(a) the school should be equipped with a certain amount of first-aid materials and equipment in accordance with the relevant provisions, and equipped with necessary first-aid drugs.
(2) It is forbidden to have classes or organize various outdoor activities outdoors in heavy rain. In case of school time, you should obey the arrangement and command of the school, and no one or class is allowed to make decisions without authorization. If necessary, inform parents to pick up students from school, especially those passing through Hetao on their way home.
(3) To strengthen the education of flood safety knowledge for teachers and students, and understand the measures and skills of flood escape and self-help. Schools should organize teachers and students to carry out necessary drills in accordance with the requirements of emergency plans for safety work in flood season.
(4) Several classes in the school should strengthen the careful investigation of the following situations and take timely measures to eliminate hidden dangers: the safety of classrooms, function halls and other buildings; Students' food hygiene and disinfection equipment; Safety of school stairs, corridors, guardrails, fences, doors and windows, toilets and sports facilities; The evacuation passage and safety exit of the personnel gathering place are unblocked; Maintenance and management of electrical appliances, equipment and lines; The flow of ditches and culverts around the campus; The safety situation of students' commuting areas, etc.
Sixth, post-treatment
The school emergency rescue leading group in flood season is responsible for the aftermath of the disaster, promptly investigate the disaster losses, and form a written report to do a good job in post-disaster treatment, restore normal teaching order and reconstruction.
;
- Related articles
- Desktop wallpaper with dynamic weather
- How to teach Chinese well in the lower grades of primary schools
- Xiao Tao's weather forecast is fifteen days.
- Reading classical Chinese through novels
- Severe weather, such as gale and hail, caused the lodging of wheat in Henan Province to be 6.5438+0.4 million mu. How to save this situation?
- Real-time weather in Fenghua tomorrow
- Is it suitable to go to Mount Tai in winter?
- Evaluation of eight nuclear +5.5-inch large-screen TCL Modada 3N Telecom Edition
- What documents do you need to go abroad?
- What are the similarities between Greek mythology and Manipur mythology?