How to compile the instruction manual of transformer
Compilation basis of 1
1. 1 transformer installation instructions
1.2 design and construction drawings
1.3 Code for Construction and Acceptance of Electrical Equipment Installation Engineering (GBJ 232-82)
1.4 article 5 "electrical devices" of the quality inspection and evaluation standard for thermal power generation projects.
2 construction content:
Oil-immersed self-cooled double-winding on-load voltage regulating transformer. Its parameters are as follows: ssz9-31500/110 phase number 3.
Rated capacity: 3 1500kVA.
Rated voltage:1158×1.5%15kv2.5%/10.5kv.
Contact group: YN, yno, d 1 1.
Conditions of use: outdoor
3 construction conditions:
3. 1 The transformer manufacturer has supplied it.
Arrived and in good condition, construction equipment in place.
3.2 There is enough space around the transformer, and it has been leveled, backfilled firmly, the roads are smooth, and the construction electricity is reliable.
3.3 Before the transformer body is in place, its foundation and track
It has passed the acceptance and reached sufficient strength.
3.4 Installation weather: The installation shall be carried out in an environment without rain, wind and relative humidity less than 75%.
4 construction procedures and methods:
The installation procedure is shown in figure 1, and the construction procedure is as follows:
4. 1 acceptance:
4. 1. 1 Check that the arrived equipment should be the same as the order contract.
4. 1.2 Check whether the body is deformed or damaged. Check that the nitrogen pressure of the transformer transported by nitrogen should be 0.0 1 ~ 0.03 MPa, and the transformer transported by oil should not leak.
4. 1.3 Check whether the spare parts and components are intact according to the manufacturer's equipment list. There should be no leakage at the secondary terminals of the transformer of the high-voltage bushing and the lifting seat, and the oil level of the high-voltage bushing should be normal.
4. 1.4 transformer instruments shall be intact and stored in a dry room.
4.2 Electrical personnel shall cooperate with the hoisting personnel to complete the positioning of the transformer body, find the center line of the transformer according to the design drawings and the B-phase center line of the low-voltage bushing, cooperate with the hoisting personnel to install the roller, and install the wheel stopper after positioning. When the oil gradient in the direction of the oil storage tank is not specified by the manufacturer, the oil storage tank side should be raised to have a gradient of 1 ~ 1.5%.
4.3 Disposal of transformer oil: Transformer insulating oil filled with nitrogen or transported with oil should be tested for pressure resistance and micro-water and qualified, otherwise it should be filtered by vacuum oil filter until it is qualified.
4.4 Transformer ontology inspection (taking nitrogen-filled transportation and hanging cover inspection as an example).
4.4. 1 Before the hanging hood is inspected, the high-voltage bushing, current transformer of lifting seat and gas relay shall pass the test.
4.4.2 Before inspection, you should know the weather conditions of the day (contact the local weather station), and it should be carried out under the condition of no rain or strong wind and relative humidity below 75%.
4.4.3 Check the materials, tools, equipment, fire-fighting appliances, etc. before the body inspection. Should be prepared, and should hang a tripod with on-load voltage regulating switch.
4.4.4 Align the hook position of the crane, and the two included angles of the lifting rope shall not be greater than 60 degrees.
4.4.5 Use a vacuum pump to discharge nitrogen until the nitrogen is under negative pressure. The place where nitrogen is discharged should be well ventilated to facilitate the diffusion of nitrogen.
4.4.6 Loosen the connecting rod between the on-load voltage regulating switch and the operating mechanism, and remember the gear position. Loosen the fixing bolts of the cover voltage-regulating switch and hang the on-load voltage-regulating switch on the prepared tripod.
4.4.7 Loosen the positioning member during transportation.
4.4.8 Lifting device body.
4.4.8. 1 Loosen the bolt at the bottom of the fastener body.
4.4.8.2 tied the diagonal of his body with two hemp ropes to keep his balance.
4.4.8.3's four round bars are used for traction.
When 4.4.8.4 is lifting, slowly lift the machine body with traction round steel. When the machine body leaves the traction, use people with four corners to stabilize the balance between the machine body and the two ropes, so that the machine body can be slowly lifted away from the iron core, and then placed on the sleepers covered with film.
4.4.9 Body inspection contents:
4.4.9. 1 During transportation, there should be no movement on the palm and all parts of the body. Temporary protection devices and support palms used for transportation shall be dismantled, counted and recorded for future reference.
All bolts in 4.4.9.2 shall be tightened and anti-loosening measures shall be taken. Insulating bolts are undamaged, and the locking and binding are good.
4.4.9.3 iron core should be free from deformation, the insulation pad between iron yoke and splint should be good, and the iron core should be grounded at multiple points. After disconnecting the grounding wire, the insulation between the iron core of the iron yoke and the grounding plate should be good, and the insulation between the iron yoke bolt and the iron core, the iron yoke and the clamp, and the screw and the clamp should be good.
4.4.9.4 insulation shell should be firmly bound, and the lead wires of all coils on the shell should be well sealed, so that the winding part should be normal.
The lead wire of 4.4.9.5 shall be insulated, firmly bound, free from damage and distortion, the fixed bracket shall be fastened, the exposed part shall be free of burrs and sharp corners, the welding shall be good, and the taper into the casing gland shall be appropriate.
4.4.9.6 should check that the switch range of on-load voltage regulating switch device should be in good contact, and the tap leads should be connected correctly and firmly. The switch part is well sealed.
4.4.9.7 should check that the sealing condition of the insulation interface between the strong oil circulation pipeline and the lower wheel is good, and check that there should be no sludge, metal chips and other sundries in each part.
After 4.4.9.8 inspection, flush and clean the bottom of the oil tank with qualified transformer oil. Tools for cleaning the site shall be complete, and no sundries shall be left in the inspection groove. The valve on the wall of the inspection tank should be flexible and indicate correctly.
4.4.9.9 returned to the bell jar. After lifting, the pull rope is oriented to make the bell jar fall steadily and slowly. Do not touch the space station or any part of the impactor. When the bell jar reaches a certain distance, the bell jar is slowly put in place with traction round steel, and when the fixing bolts are tightened, the compression of the sealing ring around the bell jar is about one third of its thickness.
4.4.9. 10 Flush the pressure regulating switch with qualified oil, and its switch position should be the same as that when it is hoisted out, and the gear number when it is reloaded should be the same as the original gear number, and then install the connecting rod after reloading. The time from calling out the pressure regulating switch to now cannot exceed 16 hours.
4.5 Installation of high and low pressure cylinders:
4.5. 1 Installing high-pressure cylinder:
4.5. 1. 1 Install the lifting seat, clean the sealing rubber gasket and groove, put it in place according to the lifting seat marks A, B and C, and bolt the positioning belt according to the lifting seat marks, and fasten it evenly and symmetrically.
4.5. 1.2 Installation of high-voltage bushing: clean the inner hole of the conductive rod and the equalizing ball, and hang about 1 ton of 1 inverted chain on the crane hook. Use nylon rope with bolts (M8 or M 10) to pass through the sleeve, and chain block hangs the sleeve on the top of the porcelain sleeve. When the bushing is about to enter the lifting seat, adjust the angle of the bushing with chain block, screw the bolt on the nylon rope into the screw hole of the high-voltage lead head, pull out the lead, hoist the bushing into the lifting seat at the same time, align the bushing flange with the flange of the lifting seat, clean the film, tighten the bolt evenly and symmetrically, and install the bushing lead joint.
4.5. 1.3 installation of medium-pressure casing: the installation method is the same as that of high-pressure casing.
4.5. 1.4 Installation of low-pressure bushing: Open the cover plate of bushing seat and fasten the low-pressure bushing (use even force when fastening to avoid bursting); Open the side cover and connect the low-voltage coil lead connector with the bushing connector (when connecting, clamp the wrench with a white sand belt and put a piece of cardboard under the connector to prevent the gasket and nut from falling into the iron core).
4.5. 1.5 installation of neutral bushing: the installation method is the same as that of high-pressure bushing.
4.5. 1.6 Installation of grounding bushing: Open the cover plate of bushing seat, put the conductor into the bushing, fasten the bushing evenly and forcefully, and install the conductor connector.
4.6 Vacuum refueling:
4.6. 1 Connect the vacuum pump to the valve source of the gas relay at the top of the oil tank, connect the oil outlet of the vacuum pump oil filter to the oil drain of the transformer, and connect the upper and lower valves of the oil purifier with transparent plastic hoses for observing the oil level.
4.6.2 Start the vacuum pump and start vacuumizing. When the vacuum degree reaches 80Pa, observe whether there is any abnormality, and then continue vacuumizing until the vacuum degree reaches the value specified by the manufacturer or the plan, and check whether the oil tank is deformed or abnormal. Fill the oil slowly under the specified vacuum, and the oil filling time should be more than 6 hours. The minimum filling height should be soaked in all coils and yoke insulation, and the vacuum time after filling should be maintained for at least 4 hours.
4.7 Installation of accessories:
Installation of cooling device:
4.7. 1. 1 Clean all headers of the radiator and find out their numbers.
4.7. 1.2 Clean the radiator with qualified transformer oil, and conduct sealing test with qualified oil according to the pressure value specified by the manufacturer. There should be no leakage within 30 minutes.
4.7. 1.3 Fix the radiator with bolts, and connect the cooling device with the machine body with connecting pipes.
4.7. 1.4 Check that the motor and blades are installed firmly and rotate flexibly without jamming, and the insulation resistance of the motor should be greater than 0.5MΩ.
4.7. 1.5 Open the lower header valve and the upper exhaust valve of the cooling device, inject oil and exhaust, and then check that the valves are flexible, the positions are correct, and the joints are well sealed.
4.7. 1.6 The insulation resistance of the oil pump motor is qualified, and there is no abnormality, vibration, overheating, oil leakage or air intake during the trial operation.
4.7. 1.7 differential pressure relay shall be verified as qualified, well sealed and reliable.
4.7.2 Installation of oil storage tank:
4.7.2. 1 Clean the oil storage tank, and fill 2Kpa pure nitrogen into the inner cavity of the diaphragm bag for sealing test. When the capsule enters the oil storage tank, the long axis of the oil storage tank should be parallel along the length direction, and the capsule mouth should be well sealed and breathe smoothly.
4.7.2.2 clean the connecting conduit, connect it according to the label in the manufacturer's manual, and tighten the bolts evenly when connecting.
4.7.2.3 installed an oil level gauge and checked whether its indication was consistent with the actual oil level.
4.7.3 Installation of gas relay: Install the gas relay horizontally, with the arrow marked on the top cover pointing to the oil storage tank, and its connection with the communication pipe should be well sealed.
4.7.4 Installation of pressure relief device: the direction is correct, the inside of valve cover and lifting seat is clean, well sealed, with accurate electrical contact and good insulation.
4.7.5 Installation of moisture absorber: The connecting pipe between the moisture absorber and the oil storage tank should be well sealed, the pipeline should be smooth and the moisture absorber should be dry. (The discolored absorbent turns blue after drying) The oil level of the oil seal should be on the oil level line.
4.7.6 Installation of hygrometer: Clean the socket of hygrometer in the body with transformer oil and inject qualified transformer oil. Tighten the temperature measuring tube of the thermometer to prevent oil leakage. Capillary tube shall not be flattened or twisted suddenly, and its bending radius shall be less than 50 mm. ..
4.8 Replenishment of oil: Replenish oil from the oil storage tank to adjust the oil level, the cooler, lifting seat, sleeve and gas relay perform electrostatic discharge and repeated exhaust, and finally adjust the oil level to meet the ambient temperature.
4.9 Overall sealing test: Conduct overall sealing test with oil pressure of 0.03 MPa for 24 hours, and there should be no leakage.
4. 10 shell grounding: the body grounding is connected to the grounding grid.
5 safety technical measures:
5. 1 Make disclosure of safety measures to all construction personnel before construction.
5.2 Tools and materials used for physical examination shall be registered one by one, and special personnel shall be assigned to take charge. Check when returning the bell cover, there should be no parts.
5.3 The ladder of the climber's body shall not be directly placed on the conductor or insulation, and the construction personnel shall not climb the conductor support.
5.4 The clothes of the personnel participating in the human body examination must be free of metal buttons and are not allowed to carry any metal objects.
5.5 The construction site shall be equipped with sufficient fire-fighting equipment, and smoking is strictly prohibited in the operation area.
5.6 Ensure the electricity utilization on the construction site.
5.7 When lifting objects, strictly abide by the lifting safety rules and regulations.
5.8 aerial work shall strictly abide by its safety rules and regulations.
6 main equipment and tools:
6. 1 45t truck crane, vacuum oil filter, vacuum pump and electric welding machine.
6.2 One manual hoist (about 1T), one hygrometer and one mercury thermometer.
7 technical quality requirements (see attached table):
Installation of voltage transformer
Transformer body installation electricity 3- 1-3
Process inspection refers to the inspection items of standard quality and quantity of standard attribute units.
Individual evaluation of actual results
Heliang
Embedded parts for foundation installation shall meet the design requirements.
Basic horizontal error mm
Distance error mm
Check the sealing performance before installation. The pressure of inflatable transportation gas is MPa 0.0 1 ~ 0.03 ~ 0.03.
Oil transportation with oil is impervious to oil, and the top cover bolts are fastened.
Oil has good insulation performance.
basis
body
as soon as...
The bushing is consistent with the main mm of the center line of the enclosed bus.
Paper tape pinch wheel
After installation, the assembly roller can rotate flexibly.
Brake installed firmly, can be
Pier and transformer and embedded parts are firmly connected.
The body grounding is mainly connected with the main grounding network reliably.
The manufacturer shall specify other allowable impact values.
The positioning device at the top of the oil tank has no deformation and crack.
- Previous article:Female breast pain: six symptoms
- Next article:Wutaishan self-help tour guide
- Related articles
- How long does it take for Zhejiang Jinhua Express to reach Changzhou Xinbei District?
- I have to work and write a copy when I am sick.
- How to write an article about the weather?
- Snowstorm weather forecast
- Matters needing attention in raising cattle in summer
- Sentences describing cold weather
- Out of breath. What's wrong? Say something.
- When is the rainy season in tropical monsoon climate?
- Sichuan-Tibet Line Cycling Day 10: Litang to Heni Township
- The weather in our city is written in English.