How to write a detailed construction log?

The first is understanding.

Requirements for filling in the construction log

1, the construction log should be filled in according to the unit project.

2. Recording time: from commencement to completion acceptance.

3. Daily records are not allowed to be interrupted.

4. Records shall be timely, true and detailed. In case of personnel changes midway, handover procedures shall be handled to maintain the continuity and integrity of the construction diary. The construction diary shall be recorded by the foreman of the building number.

The second is to be clear.

Contents to be recorded in the construction log

The contents of the construction log can be divided into five categories: basic contents, work contents, inspection contents, inspection contents and other contents.

Details that should be paid attention to in the process of filling in

1. When writing, the handwriting must be neat and clear, and it is best to write in imitation of Song Dynasty or block letters.

2. The main construction contents of the day must correspond to the construction site.

3. Maintenance records should be detailed, including maintenance parts, maintenance methods, maintenance times, maintenance personnel and maintenance results.

4. Welding records should also be recorded in detail, including welding position and welding method (arc welding, electroslag pressure welding, lap double-sided welding, lap single-sided welding, etc. ), welding current, covered electrode (agent) brand and specifications, welding personnel, welding quantity, inspection results, inspectors, etc.

5. Other inspection records must be specific and detailed, and cannot be generalized. Inspection records can be memorized in detail and can also replace construction records.

6, water, electricity must be recorded clearly start and end time, water, electricity is how to return a responsibility, whether to cause losses.