When will the construction workers have a holiday when the temperature drops in Shenmu city?

As the temperature drops in Shenmu City, construction workers generally enter the holiday in March of the following year from June 165438+ 10.

"When the temperature is lower than 5℃ for many days, most of the main body construction concrete and plastering masonry cannot be carried out, and only a few decoration and installation constructions can be carried out.

During the hot weather, the construction unit should arrange the working hours reasonably to reduce the labor intensity. If the daily maximum temperature reaches 35℃ to 37℃, measures shall be taken to shorten the continuous operation time, and outdoor overtime shall not be arranged.

The main reason is that when the temperature is lower than 5℃, the hydration heat will hardly be generated during the cement hydration reaction, which will seriously damage the concrete setting, and the concrete strength will be seriously and significantly affected, and there is almost no strength.