Construction scheme of dry hard concrete slope protection
I. Overview of the Project
The slope protection of Jianshan section (K0+000~K2+ 100) of South Huanhu Road in Kunming is C20 concrete arch slope protection. The excavation section of this section of slope is Grade III, with an average height of 23.3m, of which Grade I slope is 8m high and the slope is1:1; The secondary slope is 8m high and the slope is1:1; The average height of the third grade slope is 7m, and the slope is 1: 1. A 2.0m wide platform is set between adjacent slope protection, and C20 concrete platform drainage ditch is added. The arch skeleton is protected by spraying and planting grass. The main skeleton spacing is 3.5m, the arch height is 1.5m, the section size of the main skeleton is 0.4 m×0.2m (excluding kerbs), and the section size of the arch is 0.4m×0.2m (excluding kerbs). The main skeleton is equipped with 5 ¢25 anchor rods with a length of 3.5m, and each vault is equipped with 1 ¢25 anchor rods with a length of 3.5m, which are welded with a single layer of 655438+06 steel mesh.
Second, the construction preparation
1, raw material preparation
1), sand: Machine-made sand is used. The fine sand used must be clean, and it must not contain impurities such as grass roots and clods. The silt content of the sand should not exceed 3%.
2) Cement: Ronghua brand PO32.5# rechecked portland cement is uniformly adopted.
3) Crushed stone: The choice of crushed stone shall meet the design (mixture ratio report) and specification requirements.
4) Steel bar: Kungang steel bar shall be used uniformly.
5) Template: The template used must be smooth and flat.
2, the construction site preparation
1), the construction site should be equipped with temporary waterproof and drainage system, reasonable power system and fully equipped concrete raw material metering equipment.
2), personnel and mechanical equipment
In order to meet the construction needs, combined with the construction documents and site construction conditions, our unit is equipped with the following personnel and machinery: see the attached table for details.
Staffing list
Type of work and personnel
number of people
Technician 1
Surveyor 2
Laboratory technician 2
Concrete pouring machine 4
Formwork installer 4
Mechanic 2
Handyman 6
Reinforcement worker 4
List of construction machinery and tools
Name, model and unit quantity of mechanical equipment
JZC350 concrete mixer 1
Concrete truck platform 1
Vibrator ZN50 set 2
Borehole cleaning drill floor 3
Third, the construction period arrangement
According to the overall construction period of this contract section, combined with the construction site conditions and the configuration of people, materials, machines and materials, the planned construction period is from 2010125 October to 2010 October.
Fourth, the construction scheme and process
The arch slope protection adopts the sequence of combining small machines with manual excavation, and adopts the supporting formwork method for step-by-step construction.
1, construction lofting
According to the design documents, the positions of the transverse beams and vertical beams shall be arranged reasonably in case of any discrepancy with the design documents, and special attention shall be paid to the setting-out of the slope angle. Ensure the smoothness of the transverse and longitudinal beams and the roundness of the overall line shape. Do a good job of pile protection in time when surveying and setting out, so as to use it accurately in the later period. After surveying and setting out, the slope excavation can only be carried out after being approved by the surveying supervision engineer.
2, anchor construction
2- 1, set the working platform
According to the position of lofting drilling, the operating platform of hole cleaning rig is set, and seamless steel pipe with 3.5MM wall thickness is adopted. After installation, check whether the fasteners are fastened.
The spacing of slope support erection is horizontal1.75m and vertical 2m, and a safety net with a height of 1.5m is set every 4m. The upper and lower passages of the construction passage are 2m wide and horizontal1.2m..
2-2, drilling rig
When drilling on the slope of 1: 1, the drill pipe is drilled at 65 degrees with the slope. Slowly drill into the rock stratum, and the point error is less than 2 cm. The deviation of drilling shall not exceed 5%.
2-3, anchor positioning and grouting
Clean the hole after drilling, put the anchor into the anchor hole for the first time after welding the positioning rib, and then remove rust and oil first.
When placing the anchor rod, put the mortar conduit together with the anchor rod into the anchor hole. Immediately after anchor positioning, grout with M30 mortar, maintain grouting pressure during grouting, and slowly pull out the pipe while grouting. Finally, according to the mortar flowing out of the anchor hole, it is determined that the mortar has been filled.
3, slope excavation construction
Before construction, remove the eluvial soil on the slope surface and fill the pit to make the slope surface generally flat. Platforms between adjacent slopes should be leveled and compacted, and a certain one-way longitudinal slope should be ensured to ensure the stability of platform ditches and smooth drainage. According to the position of transverse and longitudinal beams after lofting, small machines and tools are used to cooperate with manual excavation. Unstable excavation groove bottom and slope surface should be replaced and tamped. The excavation sequence of the same grade slope is: top-down, one step in place, the bottom of the groove is dense and smooth, and overbreak is prohibited.
4, steel processing and installation
Processing and installing steel bars according to design drawings.
5, template construction
Before template installation, install the steel pipe rack stabilizer. The stable frame adopts the method of temporary anchorage of steel pipe in the slope. Then install the formwork support, and then install the formwork. Template adopts "30 15", and the template surface must be smooth and flat. When installing the formwork, the joints should be tight, the plate body should be straight, the dislocation of the formwork should be strictly controlled, and the installed formwork should ensure a certain overall stability. During formwork construction, it is necessary to ensure the straightness of the overall line type and the roundness of the overall slope. Template release agent must be daubed evenly, and waste engine oil is strictly prohibited. When the formwork is removed, it shall be removed layer by layer according to the pouring sequence of concrete, and the removed formwork shall be placed centrally, and the formwork panel shall be cleaned for next use.
6, concrete construction
The concrete pouring sequence of arch slope protection is: from bottom to top, first foundation, then vertical beam, then platform, and finally arch frame and water diversion facing stone construction.
Concrete pouring and transportation adopt the form of car+chute. In order to ensure the mixing quality of concrete, the workability and slump of concrete are strictly controlled during the mixing process. When pouring concrete, the vibrating quality should be strictly controlled. The vibrating standard is that the concrete stops sinking, no bubbles appear, and the surface is smooth and pulpy. The poured concrete should be displayed under the actual weather conditions, and the necessary watering and curing work should be done well.
Five, the construction matters needing attention
1, a settlement joint is set for slope protection every 12.0m, and asphalt wool or asphalt board is filled in the joint. The settlement joint is 2 cm wide.
2, dry excavation groove bottom should be properly watered to prevent concrete from losing too much water and causing concrete cracking.
3. The contact surface between the arch beam and the vertical beam should be chiseled or brushed, and cleaned with clear water, so that the concrete can be well combined.
4, vertical beam and arch beam embedded water separation stone position, to do hair or cut hair processing, and clean with water before embedded water separation stone, in case of poor bonding between water separation stone and beam, leading to later water separation stone fall off.
5. During the construction of platform drainage ditch, pay attention to the roundness of curves and lines and the smoothness of drainage.
6, concrete vibrating, pay attention to the phenomenon of vibrating and vibration leakage.
7, when the concrete strength reaches 2.5MPa, can be removed. Prevent concrete from falling off corners and gnawing edges.
8. Ensure the roundness of the whole slope protection and the beautiful arrangement of arch beams.
Quality assurance and control of intransitive verbs
1, establish a strict quality assurance system. The project department shall set up a full-time quality inspection engineer to be fully responsible for the quality management of the construction site; The construction team shall set up part-time quality inspectors to be responsible for on-site technical guidance and quality inspection.
2. Technicians, surveyors, and test inspectors shall operate in strict accordance with the specifications.
Seven, safety production procedures and guarantee measures
1, safety production procedures
1) Set safety signs on the construction site.
2) Set signs at the intersection of the construction service road.
3) Large construction machinery should be operated by professionals.
4) During construction in rainy season, drainage ditches, drainage ditches and water retaining weirs should be prepared in time to prevent flood from flowing backwards in flood season and affect construction safety.
2. Comprehensive safeguard measures
1) set up a leading group for safety work headed by the project manager, with full-time safety inspection engineers in the project department and full-time safety officers in the construction team responsible for overall safety work.
2) Establish various safety management systems and reward and punishment systems, and establish the responsibility system for production safety at all levels.
3) During the construction, the construction team safety officer shall conduct safety inspection at the site, report the problems to the project department in time and solve them in time. The safety leading group of the project department regularly checks the work of the construction team to help the construction team solve practical problems on site.
4) Designated persons shall be assigned to command and dispatch at the site to determine the appropriate route of mechanical vehicles and set up obvious signs to prevent mutual interference and collision.
Eight, environmental protection measures
1, the construction site set up a special person in charge of environmental protection, the responsibility to the people.
2. The construction site should be clean and tidy, and construction waste materials should be piled up in a centralized way.
3. Pay attention to soil and water conservation on the construction site, occupy farmland and cultivated land as little as possible, and ensure the circulation of the original water system. During the construction period, the normal irrigation and cultivation of farmland will not be affected.
4. Destroy the forest land as little as possible, and restore the original appearance after the project is completed.
Nine, civilized construction
1, civilized construction, orderly site management and unified planning of site layout. The materials in the construction area shall be neatly stacked, the site shall be leveled, the roads and drainage shall be smooth, and all kinds of materials and materials shall be marked correctly.
2, strengthen the management of the construction site, a clear division of labor, responsibility to the people, rewards and punishments, so as to highlight key points, implement in batches, standardize construction, and pay attention to actual results. Adhere to the construction personnel, and set up obvious signs on the construction site, mainly including construction bulletin boards and safety warning signs.
3, found in the construction of cultural relics, timely report to the local department in charge of cultural relics, and do a good job of site protection.
4. During the construction period, always maintain the construction transportation road to ensure rain or shine, which is convenient for the production and life of residents along the line. Sprinklers are used to sprinkle water frequently to reduce dust.
5, reasonable arrangement of construction work, in the residential area near the construction site, don't arrange high noise mechanical construction at night.
6. Respect local customs and abide by local laws and regulations.
FYI
- Related articles
- What should rheumatism usually pay attention to?
- Will it rain on the wedding day? Don't let the weather affect your mood?
- There will be a cos costume location tomorrow. The weather is very hot. There is a way to prevent heatstroke.
- Thousands of fine weather.
- What's the change in the weather in early autumn?
- The latest tour guide of Yichang Qingjiang Gallery 2022 One-day tour guide of Yichang Qingjiang Gallery
- Yangquan-China Weather Network 15 Weather Forecast
- How about the expressway from Handan to Shijiazhuang today?
- Why do some people's space display weather forecast and horoscope when they enter QQ space on their mobile phones? I can't tell from mine. How can we show it? ...
- The weather in Seda in July