Traditional Culture Encyclopedia - Tourist attractions - Program content of the 2010 rural radio and television village access project construction implementation plan in Daozhen Autonomous County
Program content of the 2010 rural radio and television village access project construction implementation plan in Daozhen Autonomous County
1. Project construction tasks
(1) Construction tasks. Before September 20, 2010, 37,294 households in the county must complete the "Village Access" project. The specific construction tasks of each township (town) are as follows:
Yuxi Town: 5038 households Shangba Township: 2178 households Sanjiang Town: 1936 households
Longxing Town: 4598 households Old town: 1298 Hutaoyuan Township: 1,958 households
Zhongxin Town: 1,326 households Luolong Town: 1,418 households Yangxi Town: 2,552 households
Hekou Township: 2,596 households Dajue Town: 4,246 households Sanqiao Town: 5170 households
Pingmo Town: 2618 households
The remaining 362 households will be allocated separately based on the completion status and actual needs of each township (town).
(2) Construction methods. Live broadcast and television satellite coverage.
(3) Construction funds. The funding sources for this "Village Access" project are mainly divided into four parts (funding from the state, province, city and beneficiary farmers). All national and provincial funds are invested in the form of equipment, and beneficiary farmers only need to invest 100 yuan for equipment installation and commissioning. and auxiliary material costs.
2. Principles of project construction
(1) The principle of "one guaranteed, two temporarily unarranged". "One guarantee" is to ensure that equipment is given priority to remote village groups and farmers who cannot be covered by other means (wired, wireless, etc.). The "two temporary arrangements" are that the village groups where wireless signals have been covered or will be covered in the future will not be arranged; the village groups with good economic conditions and where the cable TV project is accessible or will be accessible in the future will not be arranged.
(2) Focus on the principle of overall promotion. The implementation of the project should be planned as unified as possible and promoted in the entire area (concentrated villages with more than 20 households) to ensure that one is arranged and one is completed without leaving any omissions.
(3) The principle of mass voluntariness. Farmers in the project planning area who need to install "Village Access" equipment must fill in the "Daozhen Autonomous County Radio and Television "Village Access" Project Installation Application Form". Any application not submitted on time will be deemed to be automatically abandoned.
(4) Follow the implementation principles of the “Eleventh Five-Year Plan”. Equipment must be distributed and installed in a targeted manner, and equipment must be strictly flown into non-planned areas. If the planned area has access to cable TV or wireless coverage signals, appropriate adjustments can be made.
3. Strengthen leadership and clarify responsibilities
The radio and television “Village Access” project is the No. 1 project in rural public cultural construction in the new era and has been listed by the Municipal Party Committee and the Municipal Government. One of the "Ten Real Things". The "Every Village Access" project has many points, a wide scope, and high requirements. The work is very difficult. It must be highly unified in thinking and strictly follow the provincial and municipal principles of "the party committee and the government as the leader, the radio and television departments as the implementation body, and the radio and television network companies participate". Effectively strengthen organizational leadership and solidly and effectively promote the work of "connecting every village".
(1) Establish a leading group for the construction of the county’s “Village-to-Village” project in 2010
Team leader: Lei Houliang (Deputy Magistrate of the County People’s Government)
Deputy team leader: Ran Jianbo (Director of the County Government Inspection Office)
Yu Jiaxue (Director of the County Culture, Sports, Radio, Television and Tourism Bureau)
Members: Zheng Guoping (Director of the County Supervision Bureau)
Jiang Conglin (Director of the County Development and Reform Bureau)
Wang Guocai (Director of the County Audit Bureau)
Zhang Shuangquan (Director of the County Finance Bureau)
Jia Fuguo (Manager of the County Radio and Television Network Company)
Wan Xiaohong (Head of Yuxi Town People’s Government)
Zhou Kefang (Head of Shangba Township People’s Government)
Han Yu (Mayor of the People's Government of Sanjiang Town)
Yang Daiyong (Mayor of the People's Government of Longxing Town)
Ran Xiaoyong (Head of the People's Government of Zongping Township)
< p>Li Jingwei (Mayor of the Old Town People's Government)Zou Junhua (Head of the People's Government of Taoyuan Township)
Feng Yi (Mayor of the People's Government of Zhongxin Town)
< p>Zhou Yongqiang (Mayor of the People's Government of Luolong Town)Feng Yi (Hekou Township Head of the People's Government)
Luo Kesheng (Mayor of the People's Government of Yangxi Town)
p>Deng Guoshu (Mayor of Dayu Town People’s Government)
Wang Keling (Mayor of Sanqiao Town People’s Government)
Xie Zhongren (Mayor of Pingmo Town People’s Government) (Chief)
The leading group has an office in the County Bureau of Culture, Sports, Radio, Television and Tourism. Yu Jiaxue concurrently serves as the director of the office, and Wang Jiang and Jia Fuguo concurrently serve as deputy directors of the office.
Each township (town) must also establish a corresponding work leading group to be responsible for the specific work of the township (town) in project implementation.
(2) Clarify work responsibilities
1. The county’s “Village Access” project construction leading group: takes overall responsibility for the county’s “Village Access” project and is responsible for the implementation of the project and coordinate and guide work.
2. The county’s “Village-to-Village” project construction leading group office: responsible for equipment distribution, technical guidance, inspection and acceptance, establishment of files, statistical reporting, etc. during project construction, and keeping track of the county’s project implementation trends, And supervise and inspect the quality and progress of project construction.
3. The leading group for the construction of the "Village Access" project of the township (town): Responsible for the overall responsibility for the "Village Access" project of the township (town), and responsible for the "Village Access" project of the township (town) Project implementation, supervision and inspection, coordination and guidance.
4. Township (town) “Village Access” Leading Group Office: Responsible for publicity and mobilization, investigation, data collection and reporting, supervision and inspection in the implementation of the township (town) “Village Access” project , Assist the county radio and television network branch to do relevant work.
5. County Broadcasting and Television Network Branch: Responsible for the warehousing management, up and down transportation, installation and commissioning, fee collection, file collection, information entry, filling out and issuing certificates of "Village Access" equipment, etc.
p>
6. Member units: Establish and improve the supervision and management methods for the implementation of the "Village-to-Village" project, eliminate all violations of laws and disciplines, create an efficient, transparent and safe project construction environment, and ensure the smooth completion of project construction tasks.
(3) Establish a guarantee responsibility system
Establish a guarantee responsibility system that assigns responsibility to individuals and provides segmented guidance.
4. Strictly control key links and focus on refined management
(1) Strictly control the identification of implementation targets
1. Strictly control the launch of publicity. Propaganda and mobilization work must be carried out in strict accordance with the implementation principles, and effective measures must be taken to effectively resolve the contradiction between the small number of construction and the large demand of the masses to ensure social stability.
2. Strictly control the installation application. Farmers who meet the planning conditions and need to install "Village-to-Village" equipment must fill in the "Daozhen Autonomous County Rural Radio and Television "Village-to-Village" Project Installation Application Form" and submit a copy of the household head's ID card (or household register) at the same time , anyone who cannot provide a copy of their ID card (or household register) will not be approved.
3. Strictly control user information review. The "Village Access" implemented in 2010 all uses smart card encryption for authorization. Whether the user's information is accurate is directly related to whether the user's receiving device can accurately decode, and is the key to whether the user can listen to and watch good radio and television. Therefore, the basic information of applying farmers must be strictly reviewed to ensure the consistency and accuracy of the information. "Three guarantees" must be achieved:
= 1 \* GB2 ⑴ Ensure that user information is 100% accurate. Pay special attention to that the "name of the head of household" must be consistent with the ID card, and the ID number must be accurate. Also fill in the "Charging Time", "Equipment Collection" (including collection time, signature and seal of the recipient), "Equipment Installation Time", "Equipment Distribution List" and "Equipment Installation List".
= 2 \* GB2 ⑵ Ensure that the "name of the household head" on the toll invoice is exactly the same as the "name of the household head" on the "Roster of Village-to-Village Project Implementation Objects".
= 3 \* GB2 ⑶ Ensure that the information on the "Equipment Warranty Form" is 100% accurate. Before the equipment is distributed to households, the radio and television network company must organize specialized personnel to accurately fill in the relevant information of the "Equipment Warranty Form" according to the "Equipment Installation List". The relevant information between the two must be 100% consistent. At the same time, the "Equipment No. 3" must be pasted in accordance with relevant requirements. ” (Set-top box serial number, encrypted serial number, smart card number).
(2) Strictly control the publicity of implementation targets
Each township (town) must publish the list of implementation targets in the public column of the village committee and actively accept supervision by the masses.
(3) Strictly control charges
1. Arbitrary charges are strictly prohibited. The county radio and television network company must specify a designated person to be responsible for collecting fees according to the charging standards, and no arbitrary charges are allowed.
2. Adopt reasonable and effective charging methods. Charging and equipment distribution work are carried out simultaneously, and streamlined operations are implemented. The funds collected every day must be paid into the "Village to Every Village" account in time on the same day.
(4) Strictly control the acceptance and storage of equipment
After the equipment arrives at the county, all equipment shall be stored in the warehouse and a dedicated person will be assigned as warehouse manager to be responsible for the storage and distribution of the equipment. When the equipment arrives, it will be jointly inspected and accepted by the county "Village to Village" leading group office and the warehouse manager. Mainly check the following contents:
1. The quantity and quality of the equipment arriving.
2. Packaging situation. Check whether the equipment is packaged in accordance with relevant requirements and whether there is any obvious impact, moisture or corrosion during transportation.
3. Unboxing and random inspection. Carry out unpacking and random inspection at a rate of 1%-3%.
(5) Strictly control the distribution of equipment
The county "Village to Village" leading group office is responsible for transporting equipment to the township (town) according to the distribution plan; the township (town) is responsible Warehousing and safekeeping of the town’s equipment. The village committee assists the county radio and television network company in distributing equipment.
When distributing equipment to households, focus on the following key links:
1. It is strictly prohibited to entrust others to deliver the equipment on your behalf. The county radio and television network company should set up a special equipment distribution team. According to the installation plan, the equipment will be distributed to farmers in villages before installation.
2. Strictly abide by the equipment distribution process. = 1 \* GB2 ⑴ Notification in place: According to the project implementation plan, towns and villages assist the county radio and television network company in issuing equipment pick-up notices in advance. The notice content includes: pick-up time, pick-up location, payment amount, precautions, etc. In principle, when users receive the equipment, they must have their ID card or household register (but a copy) signed and stamped with a private seal by the head of the household.
= 2 \* GB2 ⑵ Set up a distribution window: The distribution location must be the local village committee. Before distribution, the village committee must prepare the equipment storage room, charging room, and equipment distribution room, and set up the charging room. Window, issuance window.
= 3 \* GB2 ⑶ Strictly abide by the issuance process: the first step is to review the information. Carefully check whether the user name and ID number on the invoice, ID card or household register, and "Implementation Target List" are consistent; in the second step, paste the device "No. 3" (set-top box serial number, Encrypted serial number, smart card number), after pasting is completed, the "Equipment Warranty Form" must be put back into the packaging box. In order to save time for issuance, this step can be carried out by multiple people in advance; the third step is to send the equipment out of the warehouse and fill in the user information on the "Equipment Warranty Form"; the fourth step is for the user to fill in the "Equipment Warranty Form" and "Equipment Collection List" Sign and stamp with private seal; in the fifth step, put the "Fourth Copy of Warranty Form" and "Equipment Installation Certificate" into the equipment packaging box; in the sixth step, the user is strictly prohibited from opening the equipment packaging box without permission, and strictly prevent equipment accessories, warranty If the order or installation certificate is lost, the user will be responsible for all consequences.
(6) Strictly control the quality and progress of the project
1. Adopt reasonable and effective construction organization methods. We will promote the construction of the "Village-to-Village" project by adopting the approach of "point first and then the difficult, first the easy and then the difficult". First select a town with the best basic work and construction conditions, and adopt a method of concentrating efforts to promote it village by village and town, and explore and summarize work experience. When conditions are mature, we will gradually expand the scope of implementation to ensure that the work is progressed in an orderly and solid manner.
2. Strictly control the quality of equipment installation. Installers must install equipment for users in strict accordance with technical specifications, pay special attention to the firmness and safety of the antenna, and try to be lightning-proof, wind-proof, and rain-proof. Ensure that users can listen to and watch all TV broadcasts with high quality.
3. Strictly control information entry. After the distribution of equipment in each village, the equipment distribution personnel must promptly report the "first three copies of the warranty form" to the county "Village Access" leading group office so that it can be entered into the live broadcast satellite user management system in a timely manner. When entering information, each household must be entered and reviewed to ensure accuracy.
(7) Strictly control inspection and acceptance
The construction of the "Village-to-Village" project is mainly divided into the preliminary preparation stage, the publicity and fee collection stage, and the installation and commissioning stage. The person responsible for the guarantee must go to the township (town) and village in a timely manner to inspect and guide the acceptance of the project construction at each stage. Each stage must be inspected and accepted before the next stage of work can be carried out.
5. Work flow and time arrangement
(1) Early preparation stage (March 1st - March 31st)
1. Establish work leadership group. Establish leading groups for the "Village-to-Village" construction work at the county and township (town) levels to clarify work tasks and determine staff.
2. Develop an implementation plan. Based on actual conditions, specific implementation plans for counties and townships (towns) will be formulated to further refine work tasks.
3. Do a good job in publicity and mobilization. Use various forms to publicize the relevant policies and regulations for the construction of the project to the general public in the project planning area, so that the policies implemented by the project are well known to everyone.
4. Do a good job in reporting installation for farmers. Organize farmers to fill in the "Village-to-Village Project Installation Application Form" and strictly determine the implementation targets in accordance with the project implementation principles.
5. Submit the "List of Implementation Objects" for review. Each township will submit the verified "List of Implementation Objects" to the county "Village Access" leading group for review.
6. Publicize the list of implementation targets. After the "Village-to-Village" leading group has reviewed and approved the "List of Implementation Objects", the township (town) will publish the list of implementation objects in the public column of the village committee.
7. Determine the construction team and provide technical training.
(2) Installation and commissioning phase (April 1 to September 20, 2010)
1. Do a good job in fee collection, equipment transportation and distribution.
2. Do a good job of home installation.
3. Do a good job of information entry.
(3) Comprehensive inspection and acceptance stage (September 21 to September 30, 2010)
1. Provide key assistance to village groups that have not completed construction tasks.
2. The county radio and television network company organized a comprehensive self-inspection and submitted it to the leadership group for acceptance after the self-inspection.
3. The county “Village to Village” leading group office organized relevant personnel to form an inspection and acceptance working group to conduct a comprehensive acceptance of the completed project construction.
4. Complete the completion report and submit it to the superior authority for acceptance.
6. Rewards and Punishments
(1) The county government will commend the advanced units and individuals who have performed in the construction process of the "Village Access" project. The main basis includes: completion on time Tasks and work progress quickly; be fair and impartial when implementing objects, make public announcements in a timely manner, and be recognized by the masses; actively supervise and assist network companies to do a good job in construction organization and management to ensure project progress and quality.
(2) Responsible units and individuals who are irresponsible for their work and affect the progress and quality of the project will be disqualified from the award, and the responsible persons will be dealt with seriously depending on the severity of the case.
(3) The County Bureau of Culture, Sports, Radio, Television and Tourism regards the implementation of the project as the main content of the annual work target assessment of the township (town).
- Related articles
- Which platform is better for tour groups?
- What kind of camera should I buy for traveling?
- Friends from Weifang have been helping me recently~ I would like to ask what interesting places there are in Weifang~
- What does "smart tourism" mean to tourism informatization?
- Ten scenic spots that Shandong tourism must visit.
- How to save money and time from Dalian to Xiamen?
- There are trains in Chengdu to play mahjong. What other features are there?
- Introduction of Chishan Scenic Spot in Shidao, Weihai
- Plant Elf Game Strategy Process
- When is the best time to go to Xinjiang? Which season is suitable for traveling to Xinjiang?